MS Project: Mixing Worked days with Calendar days

251 views
Skip to first unread message

John Baltimore

unread,
Oct 24, 2001, 5:54:33 PM10/24/01
to
I need to mix worked days and calendar days.

Example: First task is writing the specification, takes 7 days. So
it starts on a Monday and ends on Tuesday of the following week; fine
so far. Second task is a 30-day comment period, as in 4 weeks and 2
days, that is, 30 days by the calendar, not work days... but Project
makes it into six weeks (42 days).

How can I express this in Project? Thanks in advance for any
assistance!

John Baltimore

Jack D.

unread,
Oct 24, 2001, 6:11:59 PM10/24/01
to
Use elapsed time. You would enter the duration as "30 edays" rather than 30
days.

--
Please try to keep replies in this group. I do check e-mail, but only
infrequently.

-Jack Dahlgren, Project MVP


+++++++++++++++++++
"John Baltimore" <th...@homeNoSpam.com> wrote in message
news:5odett8mh4087bijv...@4ax.com...

John Baltimore

unread,
Oct 24, 2001, 7:46:31 PM10/24/01
to
On Wed, 24 Oct 2001 15:11:59 -0700, "Jack D." <Ja...@mvps.org> wrote:

>Use elapsed time. You would enter the duration as "30 edays" rather than 30
>days.

That did it (duh!). Thanks!

John Baltimore