Example: First task is writing the specification, takes 7 days. So
it starts on a Monday and ends on Tuesday of the following week; fine
so far. Second task is a 30-day comment period, as in 4 weeks and 2
days, that is, 30 days by the calendar, not work days... but Project
makes it into six weeks (42 days).
How can I express this in Project? Thanks in advance for any
assistance!
John Baltimore
--
Please try to keep replies in this group. I do check e-mail, but only
infrequently.
-Jack Dahlgren, Project MVP
+++++++++++++++++++
"John Baltimore" <th...@homeNoSpam.com> wrote in message
news:5odett8mh4087bijv...@4ax.com...
>Use elapsed time. You would enter the duration as "30 edays" rather than 30
>days.
That did it (duh!). Thanks!
John Baltimore