I currently have a Task Usage View that displays information up to 2049.
My project end date is 2017.
How can I customize the view to only show data up to 2017?
I have a lot of blank on the right side and that makes the printout out the
view difficult.
Thanks
DodoMSP
The magnifiying glass command will do the same.
...or did I misunderstand your question?
- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm
All views will show up to Dec 31 2049. There is no way to remove
the dates past your project end date when scrolling.
However, for printing you can control what date range you print
through the File > Print command.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project