The only way I now is to open each resource's cost table and manually
entering them. this process can be very tedious and subject to errors that
may be difficult to track.
Also, is there a way to do the same for the other cost tables (i.e., B, C,
D, or E)?
A second question around the same topic is can we use cost rates different
than those in the enterprise environment for specific projects?
--
EC
For the default cost rate (A): tis obne can be entered as cost in teh
resource sheet. If you first sort this shheet by group it is easy to enter
once then copy down.
For an elegant solution for the other rate tables I'm afraid you'll need VBA
programming.
HTH
--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
"E Carlsson" <ECar...@discussions.microsoft.com> schreef in bericht
news:3926D589-6C3D-4009...@microsoft.com...
On the View menu, click Task Usage then Insert the column "cost rate table"
This will help you easly assign the cost rate table
You can use the above for method for all the tables
To answer your second question I dont think so.However wait for more
responces from MVP's .
Hope this helps
I was afraid that you needed special programming to update the other rate
tables. Do you have some standard VBA scripts to add costs to the other rate
tables?
Thanks for your help.
--
EC
No, I'm sorry.
The objects to look up for help are
CostRateTables Collection, and
PayRates
Hope this helps
--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
"E Carlsson" <ECar...@discussions.microsoft.com> schreef in bericht
news:36AB5044-BB82-4DB7...@microsoft.com...
Did you ever figure out how to efficiently update the Resource Cost Rate
Tables? I am experiencing the same dilemma you were and would prefer to
have a more automated way to update several hundred Resource Rates.
Thanks,
K Martin
I think it is a significant deficiency of the current version of MSP and
should be addressed.
--
EC