Actual Cost not calculating for cost & material resources in MSP 2016
21 views
Skip to first unread message
Rajeev Nair
unread,
Dec 4, 2020, 7:14:03 AM12/4/20
Delete
You do not have permission to delete messages in this group
Copy link
Report message
Sign in to report message
Show original message
Either email addresses are anonymous for this group or you need the view member email addresses permission to view the original message
to
Hello All,
I created a sample project with 3 tasks.Assigned each type of resource (Work,cost & material) to each task.Baseline was set and project progress updated to 40%.The activity in which work resource was assigned showed correct EVM values.But the tasks which was assigned with cost & material resources were showing different EVM values.Actual costs in those cases found to be zero.Why is it so???Please help if anyone knows the issue.