Have you entered actual dates? Are the tasks more than 0%complete (that
fixes start dates); do theuy have constraints like must finish...?
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"stephanie" <step...@discussions.microsoft.com> schreef in bericht
news:46B8CC52-C51A-4DAE...@microsoft.com...
Welcome to this Microsoft Project newsgroup :)
Make sure you haven't set constraints by typing in dates. Insert a column
for Constraint type or View/Table/More tables.../ and select Constraint
Dates. Either way, reset them all to As Soon As Possible ( ie no
constraints).
FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm
Hope this helps - please let us know how you get on :)
Mike Glen
MS Project MVP
wrote:
"stephanie" <step...@discussions.microsoft.com> wrote in message
news:E957E83C-6BE9-4F8F...@microsoft.com...
Here's the misunderstanding: No links apply unles you enter them!
Select teh tasks to be linked, click the "Link Tasks" button!
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"stephanie" <step...@discussions.microsoft.com> schreef in bericht
news:05966FD2-5A2B-45CC...@microsoft.com...
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs
"stephanie" <step...@discussions.microsoft.com> wrote in message
news:0354CAE7-1A1E-4946...@microsoft.com...
"stephanie" <step...@discussions.microsoft.com> wrote in message
news:B0763B13-5F26-4E30...@microsoft.com...
(if you have time, please look at my problem "Summary Rows," also 8/23.
It's probbly equally simple.)
Linking fixed that glitch, too. As you had probably already guessed.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs
"stephanie" <step...@discussions.microsoft.com> wrote in message
news:8A034D45-25A8-44E5...@microsoft.com...
"stephanie" <step...@discussions.microsoft.com> wrote in message
news:8A034D45-25A8-44E5...@microsoft.com...