Microsoft Prject 2003 Updating Resource Usage

0 views
Skip to first unread message

@discussions.microsoft.com Mike

unread,
Dec 22, 2009, 9:02:01 AM12/22/09
to
In Project 2003 when i update the progress of a taskto a percentage complete,
does this automatically update the resource usage sheet ?
For example. If I have a task assigned to a resource that is 8 hrs, and I
update the task to 50% complete, I would expect to see the resource hours, on
the resource usage view change from 8 to 4
Is this incorrect ?
If so, how can i see Remaining Hours on a Resource Usage view. I don't see a
selection for this in the dropdown options.

Jan De Messemaeker

unread,
Dec 22, 2009, 9:16:09 AM12/22/09
to
Hi,
I'm afraid remaining work is indeed not available as an option in the
timescaled (the right) part of a Usage view.
You can insert remaining work as a column in the left part, and/or show both
Work and Actual Work.
Hope this helps,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"Mike" <Mike @discussions.microsoft.com> wrote in message
news:838B2488-B705-45D3...@microsoft.com...