I have a task which lasts four days. I have a resource whose calendar says
that it can work four hours a day. I have this resource assigned to this
task. When I am in the Gantt view and I take a look at the column
"duration", it says "2 days". As far as I remember this column just takes
number of hours the task takes, divides it by 8 and reports it as number of
days.
I want to know how many working days this task really takes. How can I check
it?
Do you want the resource to work 8 hours over 2 days or 16 hours
over 4 days? If the resource only works 4 hours per day and the
work is 16 hours, change the work, the duration should change.
To easily view the difference between work and duration, split your
screen to show the Task Form. (Window > Split.)
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project