Rich,
Simple, first go to Project/Sort. Set the sort for Start date, (I assume
that's what you mean by "in sequence"), and then check the option to
"permanently renumber tasks". You may or may not want to "keep outline
structure".
John
Project MVP
Just for the sake of completeness, when you uncheck Keep outline structure
there is no way to permanently renumber.
HTH
--
Jan De Messemaeker
Microsoft Project MVP
http://users.online.be/prom-ade
"John" <mje...@theriver.com> wrote in message
news:mjensen-4917DE...@msnews.microsoft.com...
> Hi all,
>
> Just for the sake of completeness, when you uncheck Keep outline structure
> there is no way to permanently renumber.
> HTH
>
> --
> Jan De Messemaeker
Jan,
Good catch. Sometimes I forget the little details. Thanks for clarifying.
John