Task bar length shortens dramatically between 30 & 31 min duration

5 views
Skip to first unread message

PatB123

unread,
Feb 8, 2010, 4:10:01 PM2/8/10
to
I have one task with a duration of 30 minutes. For some reason its task bar
is very short (shorter than 30minutes if viewing the timescale). However, if
I increase the task duration to 31 minutes then it correctly displays in the
window.

I"ve checked the tasks before and after it and have no unusual constraints
as far as I can tell. Any ideas as to what might be wrong? Thanks.

JulieS

unread,
Feb 8, 2010, 4:41:02 PM2/8/10
to
Hello PatB123,

Does the task show correct start and end times in the table?

My observation with Project 2007 is that the 30 min bar is actually
proportionately too long -- not too short. Does changing the bar
rounding (Format > Layout)seem to make a difference?

What version (including service pack) do you have installed?

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

PatB123

unread,
Feb 8, 2010, 5:52:06 PM2/8/10
to
Yes, that worked! Thanks. I'm looking in the help menu now to see exactly
what that function does.

Pat

"JulieS" wrote:

> .
>

JulieS

unread,
Feb 8, 2010, 6:04:29 PM2/8/10
to
Super. Glad to know turning off the rounding seems to work and thanks
for the feedback.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project