Multiple Lines of Text - Warning/Error

285 views
Skip to first unread message

dinked

unread,
Jan 7, 2009, 12:56:16 PM1/7/09
to
I noticed recently that one of my 2007 MPPs kept getting a warning/error
indicating that "There are multiple lines of text in the existing note.
Multiple lines of text can only be entered using the Notes tab of the Task
Information dialog box...."

At first I was befuddled since the Notes tab on a task permits multiple
lines of text. Then I checked every task with a Note to see if there was
something odd present. No luck.

Then I realized that the Comments field (File/Properties) contained multiple
lines of text (often I put stuff in there that is general in nature). After
removing that text, I no longer received the warning.

Did I "solve" this issue, or is this a flaw in Project 2007, as I never
received this error with prior versions of Project.

JulieS

unread,
Jan 7, 2009, 1:37:53 PM1/7/09
to
Hello dinked,

No, that's an old error. Comments in the File properties box appear
as a note in the Project Summary task line. If you add the Notes
field to a view and attempt to edit the text directly in the table,
you'll get that message.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

"dinked" <din...@discussions.microsoft.com> wrote in message
news:17885C36-024B-488E...@microsoft.com...

dinked

unread,
Jan 7, 2009, 1:51:19 PM1/7/09
to
Julie - Thanks for the prompt reply, but I'm not seeing the
File/Properties/Comments in the Notes of the MPP's summary task.

JulieS

unread,
Jan 7, 2009, 3:16:26 PM1/7/09
to
Hi dinked,

If you add the notes field, you aren't seeing the text entered into
the comments field on the Project summary task line (line zero?).

I just created the exact message you note by:

Showing the project summary task.
Going to File > Properties and entering a large amount of text into
the comments section.
Adding the notes field to the table and attempting to edit the note
on the project summary task line.

Julie

"dinked" <din...@discussions.microsoft.com> wrote in message

news:D6915AFF-627C-4909...@microsoft.com...

DraNoel

unread,
Sep 9, 2009, 1:28:01 PM9/9/09
to
JulieS,

Thank you for explaining the cause of the warning message. Is there a way
to suppress the message?

JulieS

unread,
Sep 9, 2009, 8:12:11 PM9/9/09
to
Hello DraNoel,

Sorry no, not to the best of my knowledge. Through VBA you can (I
think) turn off alerts and error messages, but I would not recommend
doing that as a blanket practice. I don't believe there is a way to
suppress only one message.

If you are interested in pursuing this idea through code (VBA) you
could post the question in the Project developer newsgroup.

Julie

"DraNoel" <Dra...@discussions.microsoft.com> wrote in message
news:900B9E30-5C0E-42C3...@microsoft.com...

DraNoel

unread,
Sep 10, 2009, 6:59:01 AM9/10/09
to
Thanks!

JulieS

unread,
Sep 10, 2009, 9:37:19 AM9/10/09
to
You're most welcome and thanks for the feedback.

Julie
"DraNoel" <Dra...@discussions.microsoft.com> wrote in message
news:3D72EDFD-1E36-4031...@microsoft.com...

johnott

unread,
Dec 30, 2009, 11:21:34 AM12/30/09
to
I am also getting this error.
However, other users in my organization are not getting the error - even when opening the same projects and repeating the same steps that I perform.

Google research shows that it was a glitch with Project 2003 that was allegedly corrected with SP1 for that version.

Either an old bug has resurfaced in 2007 or there is something odd about specific desktop clients (including you and me).

Does anyone know a permanent fix?
I've recently installed a PPRO2007 hotfix (kb973930) for other reasons, but still get the error.


dinke wrote:

Multiple Lines of Text - Warning/Error
07-Jan-09

Previous Posts In This Thread:

On Wednesday, January 07, 2009 12:56 PM
dinke wrote:

Multiple Lines of Text - Warning/Error

On Wednesday, January 07, 2009 1:37 PM
JulieS wrote:

Hello dinked,No, that's an old error.
Hello dinked,

No, that's an old error. Comments in the File properties box appear
as a note in the Project Summary task line. If you add the Notes
field to a view and attempt to edit the text directly in the table,
you'll get that message.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

"dinked" <din...@discussions.microsoft.com> wrote in message
news:17885C36-024B-488E...@microsoft.com...

On Wednesday, January 07, 2009 1:51 PM
dinke wrote:

Julie - Thanks for the prompt reply, but I'm not seeing the

Julie - Thanks for the prompt reply, but I am not seeing the


File/Properties/Comments in the Notes of the MPP's summary task.

"JulieS" wrote:

On Wednesday, January 07, 2009 3:16 PM
JulieS wrote:

Hi dinked,If you add the notes field, you aren't seeing the text entered into
Hi dinked,

If you add the notes field, you aren't seeing the text entered into
the comments field on the Project summary task line (line zero?).

I just created the exact message you note by:

Showing the project summary task.
Going to File > Properties and entering a large amount of text into
the comments section.
Adding the notes field to the table and attempting to edit the note
on the project summary task line.

Julie

"dinked" <din...@discussions.microsoft.com> wrote in message
news:D6915AFF-627C-4909...@microsoft.com...

On Wednesday, September 09, 2009 1:28 PM
DraNoel wrote:

JulieS,Thank you for explaining the cause of the warning message.
JulieS,

Thank you for explaining the cause of the warning message. Is there a way
to suppress the message?

"JulieS" wrote:

On Wednesday, September 09, 2009 8:12 PM
JulieS wrote:

Hello DraNoel,Sorry no, not to the best of my knowledge.
Hello DraNoel,

Sorry no, not to the best of my knowledge. Through VBA you can (I
think) turn off alerts and error messages, but I would not recommend

doing that as a blanket practice. I do not believe there is a way to
suppress only one message.

If you are interested in pursuing this idea through code (VBA) you
could post the question in the Project developer newsgroup.

Julie

On Thursday, September 10, 2009 6:59 AM
DraNoel wrote:

Re: Multiple Lines of Text - Warning/Error
Thanks!

"JulieS" wrote:

On Thursday, September 10, 2009 9:37 AM
JulieS wrote:

You're most welcome and thanks for the feedback.
You're most welcome and thanks for the feedback.
Julie


Submitted via EggHeadCafe - Software Developer Portal of Choice
BOOK REVIEW: Professional Silverlight 2 for ASP.NET Developers [WROX]
http://www.eggheadcafe.com/tutorials/aspnet/3573070a-b0b0-49e5-99c8-cddc274ec7f8/book-review-professional.aspx

JulieS

unread,
Dec 30, 2009, 12:09:30 PM12/30/09
to
Hello John,

As I noted below, the error is an old one which appears in Project 2007
as well. The best practice to avoid the error is to double click on the
task and edit the note in the Task Information dialog box.

I hope this helps. Let us know how you get along.

Julie
Project MVP

On 1a2/30/2009 11:21 AM, John Ott wrote:
> I am also getting this error.
> However, other users in my organization are not getting the error - even when opening the same projects and repeating the same steps that I perform.
>
> Google research shows that it was a glitch with Project 2003 that was allegedly corrected with SP1 for that version.
>
> Either an old bug has resurfaced in 2007 or there is something odd about specific desktop clients (including you and me).
>
> Does anyone know a permanent fix?
> I've recently installed a PPRO2007 hotfix (kb973930) for other reasons, but still get the error.
>
> dinke wrote:
>
> Multiple Lines of Text - Warning/Error
> 07-Jan-09
>
> I noticed recently that one of my 2007 MPPs kept getting a warning/error
> indicating that "There are multiple lines of text in the existing note.
> Multiple lines of text can only be entered using the Notes tab of the Task
> Information dialog box...."
>
> At first I was befuddled since the Notes tab on a task permits multiple
> lines of text. Then I checked every task with a Note to see if there was
> something odd present. No luck.
>
> Then I realized that the Comments field (File/Properties) contained multiple
> lines of text (often I put stuff in there that is general in nature). After
> removing that text, I no longer received the warning.
>
> Did I "solve" this issue, or is this a flaw in Project 2007, as I never
> received this error with prior versions of Project.
>

> <SNIP>


On Wednesday, January 07, 2009 1:37 PM
> JulieS wrote:
>
> No, that's an old error. Comments in the File properties box appear
> as a note in the Project Summary task line. If you add the Notes
> field to a view and attempt to edit the text directly in the table,
> you'll get that message.
>
> I hope this helps. Let us know how you get along.
>
> Julie
> Project MVP
>
> Visit http://project.mvps.org/ for the FAQs and additional
> information about Microsoft Project
>

> <SNIP>