Brown
The schedule and budget that is the standard way of setting up a project in
MSP is almost a textbook example of a time and materials contract.
Hopefully you create the project plan BEFORE the contract is negotiated
since it provides the basis of the negotiation and estimates. In a
signifigant project, the planning phase is itself a major phase of the
project and if you're doing this on the behalf of a client preparation of
the plan may itself be a billable service to the client, perhaps even a
separate deliverable from the project per se. After all, how can you
possibly bid on a project to produce new line of Wonder Widgets without
having a detailed product specification of those widgets and that may
involve a lot of research which you certainly wouldn't do for free. Once
you have the specifications in hand, you can analyse them as to the specific
work activities that will be required and estimate how long each part of it
will take, again, in an extensive project something you might not choose to
do for free. Even if preparing a preliminary plan is not going to be
billable, how can the contract be negotiated from any rational basis if your
side doesn't know ahead of time what the project is likely to cost and how
long it's likely to take? Coming up with those numbers is part of why we do
the plan in the first place.
You say you are having trouble getting the tasks set up. That covers a LOT
of territory <grin>. Where specifically are you running into your problems?
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs
"Brown" <fbr...@mta-inc.com> wrote in message
news:eAecDdVB...@TK2MSFTNGP11.phx.gbl...
Thanks
Brown
"Steve House [MVP]" <sjhouse.r...@to.send.hotmail.com> wrote in
message news:uNzOjPlB...@TK2MSFTNGP15.phx.gbl...
That being said, for the tasks you are having trouble with, my first thought
is to enter them with a duration that takes them to the end of their
contracted period. I'd then split the screen and in the bottom window I'd
make the task fixed duration and non-effort driven. If your resources work
a 40 hour week, an estimated work requirement of a couple of hours a week
translates to 2/40 or about 5% assignment units. Assigning at that level
gives a workload distributed evenly over the task that averages 2 hours a
week - Whether it's 1 hour this week and 3 hours next week or 2 hours all on
Tuesday or 30 minutes a day for the whole week can be taken into account
when you put in actuals later on. The actual distribution of the work
doesn't really affect either the total cost or overall schedule of the task
in question and so is of no consequence. For the last task, you'll just
have to make an educated guess as to what work will be required of those two
part-timers and use that as the basis of your assignment.
Remember, in any project plan it's only an estimate until you do the work.
If it works out your resources end up doing more or less work than your
Project file calls for, well, that's why it's called "estimating" rather
than "exacting." <grin> Some estimates turn out better than others but they
all are guesses with some degree of uncertainty until the planned events
actually happen.
What are you referring to with the abbrevs "PoP" and "PoS"?
HTH
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs
"Brown" <fbr...@knology.net> wrote in message
news:OD4p6fsB...@TK2MSFTNGP12.phx.gbl...
Brown
"Steve House [MVP]" <sjhouse.r...@to.send.hotmail.com> wrote in
message news:uTRk4Ct...@TK2MSFTNGP15.phx.gbl...
"Brown" <fbr...@knology.net> wrote in message
news:%23wXU1Ju...@TK2MSFTNGP09.phx.gbl...
Your multiple rates are easily handled with the rate information in the
resource definitions without resorting to creating multiple occurances of
the same resource. After you put in Joe Blow in the resource sheet, double
click on the ID number to the left of his name. In the Resource Information
page that opens there's a costs tab. Clicking that will show you 5 rate
tables designated A through E. When you asssign Joe to a task, you can
switch to the resource usage view and see the day-by-day workhours spread
out on the timeline. It will show the resource name and indented under it
will be the tasks to which he is assigned. Clicking on the ID number
associated with the specific task assignment gives you a details page that
includes which rate table for the resource that should be applied to that
task. In my classes I use an example of filming a movie - Betty's basic
function on our crew is as an assistant director but she can also serve as a
camera operator if needed. Her rate table A shows a standard rate of $25
per hr while rate table B shows $20 per hour. The task is "Shoot scene 3"
and Betty is assigned as one of the resources. If she's acting as an AD,
her assignment details show using rate table A. If she's acting as a second
camera operator, the assignment details will set to show rate table B is to
be applied.
A project is defined as a "time limited undertaking producing a unique
product or result." So far you haven't mentioned having done any analysis
of what that result is to be or breaking down the work into the specific
tasks required to achieve it. From what you've said so far, you don't
really have a project at all. You mentioned, for example, "two people that
are part time and will only work as required, need to spread their hours
somehow." But what work exactly will they do, what will trigger their being
required, how will you know when that requirement has begun or ended? You
need to explicitly define and quantify those variables before you can even
begin to schedule and distribute their work.
As I said before, if you're contracted just to supply manpower for 6 months,
without a clearly defined deliverable resulting from their work, and you're
looking to track their work schedules and report on contract hours by
activity consumed over time, MS Project or any project management
application for that matter is a less than optimal choice.
HTH
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs
"Brown" <fbr...@knology.net> wrote in message
news:%23wXU1Ju...@TK2MSFTNGP09.phx.gbl...
Brown
"Steve House [MVP]" <sjhouse.r...@to.send.hotmail.com> wrote in
message news:O5xbk3vB...@tk2msftngp13.phx.gbl...