I have several groupings that have a summary task and 10 milestones (0
duration) underneath. At the moment, 8 of those milestones have been
completed, 2 are incomplete, however, the percent complete on their summary
task is showing 0%. Playing around, I noticed that if I change the duration
from 0 to 1, the corrrect percent complete shows up at the summary level.
Can someone help me understand why the summary task's percent complete is
not being updated as task below it complete?
Thank you,
MikeW
My point is, it's irrelevant, and there is no point in puzzling over it
because Summary % Complete has no useful meaning, no matter how it is
arrived at.
It is certainly no indicator of anything connected with progress or
performance, and it does not provide any clue about what should be done.
--
Trevor Rabey
0407213955
61 8 92727485
PERFECT PROJECT PLANNING
www.perfectproject.com.au
"mikejw" <mik...@discussions.microsoft.com> wrote in message
news:E4482B20-F029-4611...@microsoft.com...
Jonathan
"mikejw" <mik...@discussions.microsoft.com> wrote in message
news:E4482B20-F029-4611...@microsoft.com...
% complete is based on duration and is connected with the data in the two
columns of 'Actual Duration' and 'Remaining duration'. For milestones these
data are 0 so consolidated % complete for Summary tasks would also be 0.
If for each milestone completion you want to show 10% complete, i.e with 8
milestones complete, Summary task should show 80% complete you may insert a
Text column e.g Text1 and for Summary tasks you may yourself input data
accordingly in that column. You may also customise the Gantt area to show
Text1 data alongwith the bars.
I hope it helps.
Vanita
--
Project Management consultant and trainer
vanita...@yahoo.com
Although I do not specifically cover this case, if you read my white paper
on my blog you will see how %Complete is calculated (it is weighted by
duration). In your case, the sum of all the durations is still 0 which is
what creates the problem. Should you be so inclined, visit the link below,
select Project Tips and then hunt for the white paper on Percent Complete
which explains how it is calculated.
Strangely enough, 0/0 in mathmatical terms is 1 by definition (or at best is
indeterminate). What you seek is a count of complete milestones divided by
total number of milestones. You would have to do that in two custom number
fields with formulas and then divide the results at the summary level.
--
If this post was helpful, please consider rating it.
Jim Aksel, MVP
Check out my blog for more information:
http://www.msprojectblog.com
"Jim Aksel" <JimA...@discussions.microsoft.com> wrote in message
news:5B5A1A2F-4347-4C0F...@microsoft.com...
1. Any number divided by itself is 1
2. Any number divided by 0 is infinity.
Since this doesn't make sense, it certainly is indeterminate.
We'll leave it to the math PhDs to reconcile. It will give them something
to do :)
Jim
_______________
"Trevor Rabey" wrote:
> .
>
--
Steve House
MS Project Trainer & Consultant
"mikejw" <mik...@discussions.microsoft.com> wrote in message
news:E4482B20-F029-4611...@microsoft.com...