Google Groups no longer supports new Usenet posts or subscriptions. Historical content remains viewable.
Dismiss

Adding Predecessor is not adjusting task start date

9,168 views
Skip to first unread message

Jaylene

unread,
Feb 5, 2010, 5:10:01 PM2/5/10
to
I have never had this problem before. I am specifying finish to start
predecessors for tasks, but the task dates (specifically the start dates) are
not adjusting accordingly. I have checked that there are no constraints on
the tasks, and that there is a resource assigned. What is happening?

Rod Gill

unread,
Feb 5, 2010, 6:24:21 PM2/5/10
to
Is there only one predecessor? If not, the other predecessor(s) may be
driving the task.

Is there progress on the task? If there is an Actual Start date, project
won't move a task.

If you have Project 2007 use the Task drivers toll (tool menu) and see what
it says.

--

Rod Gill
Microsoft MVP for Project - http://www.project-systems.co.nz

Author of the only book on Project VBA, see: http://www.projectvbabook.com


"Jaylene" <Jay...@discussions.microsoft.com> wrote in message
news:CC728E7D-6136-4279...@microsoft.com...

> __________ Information from ESET Smart Security, version of virus
> signature database 4839 (20100205) __________
>
> The message was checked by ESET Smart Security.
>
> http://www.eset.com
>
>
>

__________ Information from ESET Smart Security, version of virus signature database 4839 (20100205) __________

The message was checked by ESET Smart Security.

http://www.eset.com

Jack Dahlgren MVP

unread,
Feb 5, 2010, 8:38:57 PM2/5/10
to
Hit the F9 key and see if it recalculates. If so go to tools menu / options
/ calculation tab and set it to automatic.
If it doesn't, then look to see if the task has an actual start or that the
resource has working time on the day you expect them to start.

-Jack Dahlgren
http://zo-d.com/blog


"Jaylene" <Jay...@discussions.microsoft.com> wrote in message
news:CC728E7D-6136-4279...@microsoft.com...

Jan De Messemaeker

unread,
Feb 6, 2010, 2:31:50 AM2/6/10
to
HI,

Ultimately, when nothing goes, and neither Rod's nor Jack's advice help, you
may have a circular relationship.
Delete the links from and to summary tasks one by one and see whether it
solves the problem.

HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf


"Jaylene" <Jay...@discussions.microsoft.com> wrote in message
news:CC728E7D-6136-4279...@microsoft.com...

jeremyfa...@gmail.com

unread,
Apr 4, 2014, 7:35:21 AM4/4/14
to
Hey fantastic - I had exactly this problem and you saved me more gray hairs!! J.

joacim....@gmail.com

unread,
Jun 4, 2014, 9:54:02 AM6/4/14
to
I have exactly the same problem but after walking through your suggested solutions still the same problem. When I enter a new task (automatically scheduled) it doesn't go back to the project start date and I can't move it with links just with constraints.

BR

Joacim

njb...@gmail.com

unread,
Aug 5, 2014, 5:05:38 PM8/5/14
to
Joacim,

I had the same issue. Check the percent complete of the task. I found if there is any value > 0% complete the Start Date will not adjust.

Nigel

chrisa...@gmail.com

unread,
Feb 9, 2017, 9:01:08 AM2/9/17
to
Check the Summary Task for predecessor as well (sometimes it establishes a start constraint)
Message has been deleted
0 new messages