MS Project cash flow report into Excel

656 views
Skip to first unread message

Priit

unread,
Jul 16, 2009, 9:03:01 AM7/16/09
to
How can I export a MS Project cash flow report into Excel

Unknown

unread,
Jul 16, 2009, 9:15:26 AM7/16/09
to
Could you provide more detail as to what fields you are trying to export?
Timephased actual cost? Some custom fields? Timephased cost?

What would you like it to look like when it is exported?

Priit

unread,
Jul 16, 2009, 10:01:02 AM7/16/09
to
I would like to export the cost of the month with all the tasks, including
top level tasks.

At the moment I see the cash flow report, only the cost of the task but not
top level task cost?

"Andrew Lavinsky" kirjutas:

Unknown

unread,
Jul 17, 2009, 10:28:48 AM7/17/09
to
I am still not sure I follow. Are we talking MS Project 2007 or 2003?

In MS Project 2007, there are three "Cash Flow Reports:"

1) Report > Reports > Costs > Cash Flow
2) Report > Visual Reports > Cash Flow (Visio)
3) Report > Visual Reports > Cash Flow (Excel)

I suspect that we're talking about the last option. When I create that report,
the default view does not include tasks. When I drag them from the right
hand column to the table, it displays tasks with the project summary task,
and allows me to select the level at which I want to see the data. Further
moving the time element to the top, allows me to see all costs by tasks across
time, including the project summary task.

Is this what you're looking for?

-A

Mike Glen

unread,
Jul 19, 2009, 6:23:06 PM7/19/09
to
Hi ,

Try posting on the developer newsgroup as this one is closing down. Please
see FAQ Item: 24. Project Newsgroups. FAQs, companion products and other
useful Project information can be seen at this web
address:http://project.mvps.org/faqs.htm .

Mike Glen
Project MVP

"Andrew Lavinsky" <(Catapult Systems)> wrote in message
news:c4abab721ff3b8...@msnews.microsoft.com...