When I view the tasks for the resource in the resource center my project and
all the tasks are listed. He is his own assignment owner.
Is there something I'm doing wrong.
Thank you,
Leilani831
If you open the project and then click Tools - Build Team from Enterprise,
is the Booking value for the resource set to Committed? If not, change it
from Proposed to Committed and then republish the project. Let us know if
this helps.
--
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"
"Leilani831" <Leila...@discussions.microsoft.com> wrote in message
news:50686FC2-E7A9-468A...@microsoft.com...
Hanni
"Dale Howard [MVP]" wrote:
> .
>
1) Are you sure the resource is logging into PWA with his own credentials?
Sometimes the wrong ones can get stuck in there. Click on the option in
the top right to log out and back in.
2) Are you sure the resource is going to the right PWA site? Sometimes folks
get PROD and TEST mixed up and log in to the wrong ones.
- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm
When playing with the filters we were able to get one of the tasks appear.
Could it be something with the project or task view? Will they appear
eventually?
Thank you,
Lelani831
"Andrew Lavinsky" wrote:
> .
>
Prasanna Adavi
Leilani831 wrote:
I am sure the resource is logging into PWA with his own credentials.
02-Dec-09
I am sure the resource is logging into PWA with his own credentials. He sees
other tasks from other projects, just not the new ones I assigned, but I see
them in the resource center under his name so I know the right resource is on
the project. He does not have access to the other PWA sites, just the
production environment.
When playing with the filters we were able to get one of the tasks appear.
Could it be something with the project or task view? Will they appear
eventually?
Thank you,
Lelani831
"Andrew Lavinsky" wrote:
Previous Posts In This Thread:
Submitted via EggHeadCafe - Software Developer Portal of Choice
In - Memory Data Compression with .NET PART II
http://www.eggheadcafe.com/tutorials/aspnet/e9697b6e-d3ae-46b8-80bc-144ff77d8cff/in--memory-data-compress.aspx