RE: Applying resource calendar

3 views
Skip to first unread message

Ben Howard

unread,
Mar 11, 2008, 9:42:00 AM3/11/08
to
I'm not sure I understand exactly the problem, except that you have a
milestone that occurs on a Sunday and that you don't know why. Please expand
on exactly which working days your calendars have, and which calendars are
associated with the project, task, resource etc. That way I might be able to
help.
--
Thanks, Ben.
http://appleparkltd.spaces.live.com/

"ein" wrote:

> Hi,
>
> I have in my plan 2 resources with different calendars (the project calendar
> is the same as one of the resource).One of the resource is assigned to a
> milestone. the day of the week of the milestone is not like the calendar of
> this resource(e.g. it has standard calendar, but Sunday is the day that
> appears).How can this be resloved?
> Thanks, Ein