Error summary/areas:
Notification message processor failed
NotificationEMailDeliveryFailed
Queue
GeneralQueueJobFailed
Error details:
<?xml version="1.0" encoding="utf-16"?>
<errinfo>
<general>
<class name="Notification message processor failed">
<error id="16080" name="NotificationEMailDeliveryFailed"
uid="0aa867e1-4d96-4c59-93b5-c073720a841b"
EmailTypeUID="01ccf525-2cb1-4181-bc80-535a6db16c05" Error="Fail to deliver
the email using the SMTP server 'msproject.swifttrade.com' on port '25'." />
..
..
..
</class>
<class name="Queue">
<error id="26000" name="GeneralQueueJobFailed"
uid="19abf5ed-d564-4fc4-b425-bc9703072741"
JobUID="545d30b3-f1ea-490d-b9eb-12a3333249bf" ComputerName="MSPROJECT"
GroupType="NotificationMessage" MessageType="CompositeNotification"
MessageId="1" Stage="" />
</class>
</general>
</errinfo>
Anyone have any ideas how to resolve this one?
Thanks
Did you do both of the following:
1. Log into PWA with administrator permissions, then click Server
Settings - Alerts and Reminders. On the Alerts and Reminders page, enter
the correct information about your organization's SMTP e-mail server and
then click the Save button.
2. Work with your organization's e-mail administrator to set up your e-mail
system to relay e-mail messages sent by Project Server 2007.
Please note that I'm not a guru on Exchange or other e-mail servers, but I
believe #2 above is a pretty common oversight in setting up Project Server's
e-mail messaging. Let us know what you find.
--
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"
"Jonathan" <Jona...@discussions.microsoft.com> wrote in message
news:AA6FBD44-D131-466E...@microsoft.com...
Oops! I forgot one of the requirements. In your Enterprise Resource Pool,
do each of your resources have a valid e-mail address entered? When you
open the Enterprise Resource Pool for editing, double-click the name of any
resource and you can determine whether you have entered e-mail addresses for
each resource. Let us know what you find.
--
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"
"Jonathan" <Jona...@discussions.microsoft.com> wrote in message
news:AA6FBD44-D131-466E...@microsoft.com...