How to undo Checkout of a project ?

447 views
Skip to first unread message

Vivek Somani

unread,
Jul 12, 2005, 1:40:03 AM7/12/05
to
Hi,

I checked out a project from project server and was working on it. Then
suddenly my PC was hung (windows users ) and I had to restart it . I could
not close the project properly.

Now after restart when I try to open the same project in read-write mode,it
does not allow me. It shows that the project has already been checked out
byme. :-(

What should I do?

I cannot even open it for "Read only". IT throws error- "The document table
could not be opened. Contact your server administrator"

Pls help

--
Lets Learn And Grow Together

Marco

unread,
Jul 12, 2005, 3:43:02 AM7/12/05
to
Hi Vivek,

1. Login as Administrator on PWA
2. goto "Manage enterprise features"
3. Select "check in enterprise projects"
4. Select your project and click "check-in"

Marco.

Vivek Somani

unread,
Jul 13, 2005, 3:05:02 AM7/13/05
to
Thanks Marco.

Your suggestions did the trick. That's exactly what I required


--