Google Groups no longer supports new Usenet posts or subscriptions. Historical content remains viewable.
Dismiss

Custom Cost fields don't rollup?

1,461 views
Skip to first unread message

Mike

unread,
May 4, 2007, 6:36:10 PM5/4/07
to
I'm trying to use a task-level custom cost field and I can not seem to
get it to roll up. It was created in Project Server 2007 as a Task
Entity, Cost Type, Rollup(sum). I have a cost resource assigned to
one of my summary tasks and I exposed my custom Cost field on the Task
Usage view along with the built-in "Cost" column. If I enter a value
into my custom Cost field, it does not rollup. If I enter into the
built-in "Cost" column, it rolls up exactly the way I want. However,
we cannot use the "Cost" field because of it's depencency on
"Remaining Cost" and "Actual Cost." I have tried the "Calculate Now"
button on Tools > Options > Calculation to no availl.

Here are our requirements for this issue:
- Need to use Cost Resources.
- Need to assign the cost resources at the summary task (customer
requirement)
- Need to enter cost in a custom field.
- Need the total cost to roll up at all levels and within groups in
custom views.

Is this by design or is this workable?

Best Regards,
-- Mike

Marc Soester [MVP]

unread,
May 5, 2007, 8:20:01 PM5/5/07
to
Hi Mike,

Open MS Project. You will need to go to Tools > Customise > Fields.
Find your task cost field you whish to use. Under "Calculation for task and
group summary rows, tick on the "Rollup" and then choose "sum" from the drop
down window. Now your Cost field should sum up.

Hope this helps
--
Marc Soester [MVP]
State Manager: EPM
http://marcsoester.blogspot.com

Mike

unread,
May 7, 2007, 5:38:04 PM5/7/07
to
Marc..

Thanks for the reply, however, this doesn't work. The "Rollup" option
is greyed out because I am using an Enterprise custom field with
Project Server 2007. The field was created as a task entity, cost
type, with rollup(sum) selected. You'd think that with these options,
it would rollup. It just isn't doing it for me.

Did your posted solution work for you when using server?

-- Mike

Marc Soester [MVP]

unread,
May 8, 2007, 8:04:20 AM5/8/07
to
hmmmm, I am surprised that this doesnt work. Let me have a look. I will get
back to you

--
Marc Soester [MVP]
State Manager: EPM
http://marcsoester.blogspot.com

Marc Soester [MVP]

unread,
May 10, 2007, 4:48:00 AM5/10/07
to
Hi Mike,

sorry for the delay, somethimes live is just busy :)
I have tested this on Project Server 2007 and it works. This is what I have
done
Go to PWA > Server Settings > Enterprise Custom fields > New Field
- Next Screen
Enter a name of the custom field, choose Entity = Task and Type = Number (
or cost)
Custom Attributes = None
Calculation for Summary Rows = Rollup and then choose Sum
Leave the rest as is. Save the new field.
Open Project Professional and Insert the column wiht the custom field you
just created. When entering data, you will see that the number sums up on the
summary field
I hope this does the job for you :)

--
Marc Soester [MVP]
State Manager: EPM
http://marcsoester.blogspot.com

tasanton

unread,
May 24, 2007, 11:49:00 AM5/24/07
to
Marc hi,

I have the same exact problem with Mike. An enterprise CF of type
number/cost is not rolled up inside P2007. The summary task always shows
#ERROR.

Any ideas ?

Marc Soester [MVP]

unread,
May 24, 2007, 10:37:00 PM5/24/07
to
Hi tasanton,

can you please varify that you have set up the custom fields as I explained
in my last post.
Thanks
Marc


--
Marc Soester [MVP]
State Manager: EPM
http://marcsoester.blogspot.com

Tasanton

unread,
Jun 1, 2007, 5:08:00 PM6/1/07
to
Hi Marc,

Yes, it's fairly simple but it doesn't work:

- Create a new task custom field "Invoice" of cost type with rollup(sum).
- Create a new project and enter 1 summary task and 1 subtask.
- Enter 1000 in the "Invoice" field in the subtask.
- #ERROR shown in the summary task.

I've noticed similar issues with type number too.

Marc Soester [MVP]

unread,
Jun 1, 2007, 8:26:01 PM6/1/07
to
Hi Tasanton,

try not to enter a value in a summary task only at a lowest level task and
see if you still receive the error message
Let me know. thanks


--
Marc Soester [MVP]
State Manager: EPM
http://marcsoester.blogspot.com

Tasanton

unread,
Jun 3, 2007, 9:10:01 AM6/3/07
to
Marc,
I am not entering any value in the summary task.
I expect it to be calculated based on the rollup(sum) of the child task.
Instead, I am getting an #ERROR.

T

Marc Soester [MVP]

unread,
Jun 3, 2007, 9:53:01 PM6/3/07
to
Tasanton,

I have been trying it again and it still seem to work.

Can you please ensure to follow these steps:


Go to PWA > Server Settings > Enterprise Custom fields > New Field
- Next Screen
Enter a name of the custom field, choose Entity = Task and Type = Number (
or cost) > Custom Attributes = None
Calculation for Summary Rows = Rollup and then choose Sum
Leave the rest as is. Save the new field.
Open Project Professional and Insert the column wiht the custom field you
just created. When entering data, you will see that the number sums up on the
summary field

If this doesnt work and you dont have an error in either your queu or the
event log, then I dont know why it doesnt work for you
Sorry

Tasanton

unread,
Jun 4, 2007, 4:27:00 PM6/4/07
to
Hi Marc,

I think I found the reason behind the erroneous behavior.
It seems that if you define a field which is formula-based and is not
working ok (message: syntax error or unrecognized field), then this field
affects others in P2007. I had such a field and when I corrected it, the
number/cost fields started behaving correctly and rollup.
Now it may not be as simple as it sounds, because I am also using a
locale<>EN and have some issues with the list separator.

Anyway, it's fine now. Thanks Marc for your assistance !

Morales@discussions.microsoft.com Miguel Morales

unread,
Aug 15, 2007, 12:46:07 PM8/15/07
to
Marc, I'm also having this issue, but here is what I found so far. Please
tell me if I'm not reading this correct.

I have a Enterprise Custom Field label [Bill Rate] task, cost type. I then
have another ECF label [Total Billed Rate] task, cost type with a formula
[Bill Rate]*[Work]/60, I select to roll it up, and select SUM. the fields
saves fine, but when I go back and look at the properties of the field, the
roll up option has moved to FORMULA?????
Its fair to say that if I do not use a formula the roll up feature works
fine….
I get the "ERROR" in the summary cell for the [Total Bill Rate] is this a
field type and formula limitation?????
Is there a way to build the formula so it rolls up????
Thanks
Miguel

Mike

unread,
Aug 16, 2007, 5:07:20 AM8/16/07
to
On Aug 15, 5:46 pm, Miguel Morales <Miguel

Mora...@discussions.microsoft.com> wrote:
> Marc, I'm also having this issue, but here is what I found so far. Please
> tell me if I'm not reading this correct.
>
> I have a Enterprise Custom Field label [Bill Rate] task, cost type. I then
> have another ECF label [Total Billed Rate] task, cost type with a formula
> [Bill Rate]*[Work]/60, I select to roll it up, and select SUM. the fields
> saves fine, but when I go back and look at the properties of the field, the
> roll up option has moved to FORMULA?????
> Its fair to say that if I do not use a formula the roll up feature works
> fine....
> > > > > > > > > > -- Mike- Hide quoted text -
>
> - Show quoted text -

Miguel

I believe there is a bug. Whenever you choose rollup (or none), close
the edit and then re-edit the field the summary calculation option is
always displayed as formula, however when you save the field with
summary set to rollup or none, this setting is effective (so a problem
with the form rather than the setting). In my experience you can set
detail to a formula and the summary to a function successfully

regards

Mike (2)

Ian Symes

unread,
Aug 4, 2010, 12:24:58 AM8/4/10
to
Hi Marc, and others... this is trail has been going some time, and I have just hit the same problem. We had done the Custom Field setup in our test environment with no issues. When we recreated them in our live environment, the roll-ups on enterprise fields were rolling up to error.

Having read through this post, we eventually removed all calculated Enterprise fields (there were only 4), and tested - fields rolled up ok. Now we are recreating the formula based fields, and we seem to be ok.

My thoughts are that EPM had retained some information about fields we had 'played with' in the past, and was either confused or using incorrect information until we completely deleted the fields.

Thanks for your lead on us tracking down the source of our issue!

Ian

Miguel Morale wrote:

Marc, I'm also having this issue, but here is what I found so far.

15-Aug-07

Marc, I'm also having this issue, but here is what I found so far. Please
tell me if I'm not reading this correct.

I have a Enterprise Custom Field label [Bill Rate] task, cost type. I then
have another ECF label [Total Billed Rate] task, cost type with a formula
[Bill Rate]*[Work]/60, I select to roll it up, and select SUM. the fields
saves fine, but when I go back and look at the properties of the field, the
roll up option has moved to FORMULA?????
Its fair to say that if I do not use a formula the roll up feature works

fine???.


I get the "ERROR" in the summary cell for the [Total Bill Rate] is this a
field type and formula limitation?????
Is there a way to build the formula so it rolls up????
Thanks
Miguel


"Marc Soester [MVP]" wrote:

Previous Posts In This Thread:

On Friday, May 04, 2007 6:36 PM
Mike wrote:

Custom Cost fields don't rollup?


I'm trying to use a task-level custom cost field and I can not seem to
get it to roll up. It was created in Project Server 2007 as a Task
Entity, Cost Type, Rollup(sum). I have a cost resource assigned to
one of my summary tasks and I exposed my custom Cost field on the Task
Usage view along with the built-in "Cost" column. If I enter a value
into my custom Cost field, it does not rollup. If I enter into the
built-in "Cost" column, it rolls up exactly the way I want. However,
we cannot use the "Cost" field because of it's depencency on
"Remaining Cost" and "Actual Cost." I have tried the "Calculate Now"
button on Tools > Options > Calculation to no availl.

Here are our requirements for this issue:
- Need to use Cost Resources.
- Need to assign the cost resources at the summary task (customer
requirement)
- Need to enter cost in a custom field.
- Need the total cost to roll up at all levels and within groups in
custom views.

Is this by design or is this workable?

Best Regards,
-- Mike

On Saturday, May 05, 2007 8:20 PM
MarcSoesterMV wrote:

Hi Mike, Open MS Project. You will need to go to Tools > Customise > Fields.
Hi Mike,

Open MS Project. You will need to go to Tools > Customise > Fields.
Find your task cost field you whish to use. Under "Calculation for task and
group summary rows, tick on the "Rollup" and then choose "sum" from the drop
down window. Now your Cost field should sum up.

Hope this helps


--
Marc Soester [MVP]
State Manager: EPM
http://marcsoester.blogspot.com


"Mike" wrote:

On Monday, May 07, 2007 5:38 PM
Mike wrote:

Marc..Thanks for the reply, however, this doesn't work.
Marc..

Thanks for the reply, however, this doesn't work. The "Rollup" option
is greyed out because I am using an Enterprise custom field with
Project Server 2007. The field was created as a task entity, cost
type, with rollup(sum) selected. You'd think that with these options,
it would rollup. It just isn't doing it for me.

Did your posted solution work for you when using server?

-- Mike

On Tuesday, May 08, 2007 8:04 AM
MarcSoesterMV wrote:

hmmmm, I am surprised that this doesnt work. Let me have a look.
hmmmm, I am surprised that this doesnt work. Let me have a look. I will get
back to you
--
Marc Soester [MVP]
State Manager: EPM
http://marcsoester.blogspot.com


"Mike" wrote:

On Thursday, May 10, 2007 4:48 AM
MarcSoesterMV wrote:

Re: Custom Cost fields don't rollup?
Hi Mike,

sorry for the delay, somethimes live is just busy :)
I have tested this on Project Server 2007 and it works. This is what I have
done
Go to PWA > Server Settings > Enterprise Custom fields > New Field
- Next Screen
Enter a name of the custom field, choose Entity = Task and Type = Number (
or cost)
Custom Attributes = None
Calculation for Summary Rows = Rollup and then choose Sum
Leave the rest as is. Save the new field.
Open Project Professional and Insert the column wiht the custom field you
just created. When entering data, you will see that the number sums up on the
summary field
I hope this does the job for you :)

--
Marc Soester [MVP]
State Manager: EPM
http://marcsoester.blogspot.com


"Marc Soester [MVP]" wrote:

On Thursday, May 24, 2007 11:49 AM
tasanto wrote:

Marc hi,I have the same exact problem with Mike.
Marc hi,

I have the same exact problem with Mike. An enterprise CF of type
number/cost is not rolled up inside P2007. The summary task always shows

Any ideas ?

"Marc Soester [MVP]" wrote:

On Thursday, May 24, 2007 10:37 PM
MarcSoesterMV wrote:

Hi tasanton, can you please varify that you have set up the custom fields as I
Hi tasanton,

can you please varify that you have set up the custom fields as I explained
in my last post.
Thanks
Marc
--
Marc Soester [MVP]
State Manager: EPM
http://marcsoester.blogspot.com


"tasanton" wrote:

On Friday, June 01, 2007 5:08 PM
Tasanto wrote:

Re: Custom Cost fields don't rollup?
Hi Marc,

Yes, it's fairly simple but it doesn't work:

- Create a new task custom field "Invoice" of cost type with rollup(sum).
- Create a new project and enter 1 summary task and 1 subtask.
- Enter 1000 in the "Invoice" field in the subtask.
- #ERROR shown in the summary task.

I've noticed similar issues with type number too.


"Marc Soester [MVP]" wrote:

On Friday, June 01, 2007 8:26 PM
MarcSoesterMV wrote:

Hi Tasanton, try not to enter a value in a summary task only at a lowest level
Hi Tasanton,

try not to enter a value in a summary task only at a lowest level task and
see if you still receive the error message
Let me know. thanks
--
Marc Soester [MVP]
State Manager: EPM
http://marcsoester.blogspot.com


"Tasanton" wrote:

On Sunday, June 03, 2007 9:10 AM
Tasanto wrote:

Marc, I am not entering any value in the summary task.
Marc,
I am not entering any value in the summary task.
I expect it to be calculated based on the rollup(sum) of the child task.
Instead, I am getting an #ERROR.

T


"Marc Soester [MVP]" wrote:

On Sunday, June 03, 2007 9:53 PM
MarcSoesterMV wrote:

Tasanton,I have been trying it again and it still seem to work.
Tasanton,

I have been trying it again and it still seem to work.

Can you please ensure to follow these steps:
Go to PWA > Server Settings > Enterprise Custom fields > New Field
- Next Screen
Enter a name of the custom field, choose Entity = Task and Type = Number (
or cost) > Custom Attributes = None
Calculation for Summary Rows = Rollup and then choose Sum
Leave the rest as is. Save the new field.
Open Project Professional and Insert the column wiht the custom field you
just created. When entering data, you will see that the number sums up on the
summary field

If this doesnt work and you dont have an error in either your queu or the
event log, then I dont know why it doesnt work for you
Sorry

--
Marc Soester [MVP]
State Manager: EPM
http://marcsoester.blogspot.com


"Tasanton" wrote:

On Monday, June 04, 2007 4:27 PM
Tasanto wrote:

Hi Marc,I think I found the reason behind the erroneous behavior.
Hi Marc,

I think I found the reason behind the erroneous behavior.
It seems that if you define a field which is formula-based and is not
working ok (message: syntax error or unrecognized field), then this field
affects others in P2007. I had such a field and when I corrected it, the
number/cost fields started behaving correctly and rollup.
Now it may not be as simple as it sounds, because I am also using a
locale<>EN and have some issues with the list separator.

Anyway, it's fine now. Thanks Marc for your assistance !


"Marc Soester [MVP]" wrote:

On Wednesday, August 15, 2007 12:46 PM
Miguel Morale wrote:

Marc, I'm also having this issue, but here is what I found so far.
Marc, I'm also having this issue, but here is what I found so far. Please
tell me if I'm not reading this correct.

I have a Enterprise Custom Field label [Bill Rate] task, cost type. I then
have another ECF label [Total Billed Rate] task, cost type with a formula
[Bill Rate]*[Work]/60, I select to roll it up, and select SUM. the fields
saves fine, but when I go back and look at the properties of the field, the
roll up option has moved to FORMULA?????
Its fair to say that if I do not use a formula the roll up feature works

fine???.


I get the "ERROR" in the summary cell for the [Total Bill Rate] is this a
field type and formula limitation?????
Is there a way to build the formula so it rolls up????
Thanks
Miguel


"Marc Soester [MVP]" wrote:

On Thursday, August 16, 2007 5:07 AM
Mike wrote:

Re: Custom Cost fields don't rollup?

Miguel

regards

Mike (2)


Submitted via EggHeadCafe - Software Developer Portal of Choice
A Comparison of Managed Compression Algorithms
http://www.eggheadcafe.com/tutorials/aspnet/71485ecc-2d2d-435a-9c35-3d12b279f9ae/a-comparison-of-managed-compression-algorithms.aspx

0 new messages