Archiving Old Plans

0 views
Skip to first unread message

Rob

unread,
Jan 23, 2007, 11:06:00 AM1/23/07
to
Is the only process really to save the old plan on say the Sharepoint Site
and then upload the plan via Enterprise loading to the Archive Server?
Or is there more to it then that?

--
REJ Company

Dale Howard [MVP] dot at dot

unread,
Jan 23, 2007, 4:51:50 PM1/23/07
to
REJ --

There is no default method to archive completed projects. Refer to the
following FAQ for a process to archive completed projects in the Project
Server database:

http://www.projectserverexperts.com/Shared%20Documents/ArchiveCompletedProjects.htm

Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"

"Rob" <r...@rejcompany.com> wrote in message
news:CA10CA74-EE65-4777...@microsoft.com...

Rob

unread,
Jan 25, 2007, 8:49:01 AM1/25/07
to
Thats interesting, but over time wouldn't the database become overloaded with
information. I was thinking of a third server [DEV, PRD, ARCH] to extract or
import the schedules as well as resources from PRD to ARCH server. This way
the old information can be deleted out of PRD, but still mantained and
useable in ARCH.
--
REJ Company

Dale Howard [MVP] dot at dot

unread,
Jan 25, 2007, 10:08:23 AM1/25/07
to
REJ --

Some organizations require that all the info remainin in the Project Server
database, which can make a very big database. Given your concerns, you
might want to look at the following tool for automatic archiving:

http://projectmadeeasy.com/archive.htm

Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"

"Rob" <r...@rejcompany.com> wrote in message

news:C91CEFE8-D835-46C1...@microsoft.com...

Rob

unread,
Jan 25, 2007, 10:35:00 AM1/25/07
to
Thxs Dale I think a 3rd Server might be the way to go and co-exist
--
RJ
Project Consultant

Gaurav Wason

unread,
Apr 5, 2007, 5:08:06 PM4/5/07
to
Rob,

If you are interested in seeing the demo of this tool. Please contact me I
am sure this tool will help you acheive what you are looking for.

Thanks
--
Gaurav Wason
gwa...@gmail.com
MCP - Project Server
Project Made Easy
Project Archive Tool
Project Owner Tool
http://projectmadeeasy.com