I want "work” field displayed in days not hours in PWA

1,487 views
Skip to first unread message

Jaya

unread,
Oct 3, 2008, 4:34:01 PM10/3/08
to
In MS project plan by changing the way that the Work unit is displayed

1.On the Tools menu, click Options, and then click the Schedule tab.
2.In the Work is entered in box, select the time unit you want.
3.make the new settings the default in future projects, click Set as Default.

I have now made this change in the Global Enterprise template but I’m still
not seeing it showing up on my web client within the Timesheet view.

I also tried changing it for a published project (within the project plan,
not the global template) but no luck.

Finally I created a brand new test project plan and assign myself some tasks
and publish it.This works fine i can see work field as days not in hours in
web access.But i want to display the same thing for old projects plans also.

CQ

unread,
Oct 6, 2008, 5:32:19 PM10/6/08
to
I believe that after you make a change to the Global Template that you will
have to re-publish every schedule that is appearing in the view. This is how
the "old" schedule gets updated on the server.