2 views
Skip to first unread message

Joe Morton

unread,
Jan 19, 2010, 6:02:01 PM1/19/10
to
Help! Each time I open the Task Updates for Approval view it displays a date
range that starts years ago! Right now it starts at April 21, 1999. I have to
manually change the date range to something current or scroll over to the
current period if i want to see Actuals.

How do I set the start date to DEFAULT to a more current date ????

-- Joe

Gary Chefetz

unread,
Jan 20, 2010, 10:46:16 AM1/20/10
to
Joe:

The page responds to the data it receives. I suspect that if you look at the
projects, you have a project with a bad date in it.

--
Gary L Chefetz, MVP, MCT, MCITP
msProjectExperts http://www.msprojectexperts.com
FAQs and Reference http://www.projectserverexperts.com
BLOG: http://projectserverhelp.com

"Joe Morton" <J...@discussions.ms.com> wrote in message
news:106FBAAD-A515-4011...@microsoft.com...

Dale Howard [MVP]

unread,
Jan 20, 2010, 11:31:52 AM1/20/10
to
Joe --

If an enterprise project contains a very long-Duration task, spanning
months, quarters, or even years, the Task Updates page will always default
to the Start date of that long-Duration task. This is the default behavior
of the tool, by the way. Does this explain your issue? Let us know.

--
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"