Can't view projects in Project Center

2,481 views
Skip to first unread message

JasFr

unread,
Feb 10, 2010, 3:27:04 PM2/10/10
to
Hello, still new to Project and learning plenty. I've managed to get Project
Web Access up and running, synch A.D. users and upload projects.

Problem: I can't view (literally, they don't appear in the Project Center"
area) any of the published projects. I am able to view all resources,
including those that were added during publishing.

When I go to Project Center, I get this message:
"There are no projects to view in Project Center. This is because you might
not have permissions on any projects or no projects are published."

I am a local admin on the server and an administrator in Project Web Access.
I am also have rights on all 4 Project databases.

When I go to Server Settings --> Delete Enterprise Objects all of the
projects show up in the list of deletable projects. Also, if I try to open
the projects from the server using Project Professional 2007 they appear and
open fine.

I have tried using the View Effective Rights Tool for 2007 on the server and
it shows me as having permission for any project I check.

Is there anything that I need to do after uploading a project from Project
Professional 2007 to a default installation of Project Web Access? Event the
simplest thing could help, I'm open to anything really as I've tried
everything I can think of.

Thanks for any help!

kahuna

unread,
Feb 10, 2010, 4:23:01 PM2/10/10
to
JasFR - I believe you could tray a few things... First, could you check
Server>Security> Project Web Access Permissions page to see if global
permissions are set up to view projects in the project center. Also, ensure
the same is granted in the Security Templates page for Administrators, which
you can then use on the Project Manager category under Manage Categories. And
finally, you can check your user permissions under Manage Users and ensure
the same is set up.

Unknown

unread,
Feb 10, 2010, 4:31:43 PM2/10/10
to
Gotta be a security issue - unless you somehow added filters to the views
without realizing it. My guess is that it's a Category issue. Are you using
default security permissions, or have you modified them in any way. If you
have modified them, then how did you do so?

Does the project owner have the same issue for their own projects? (or are
you the project owner)

- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm

JasFr

unread,
Feb 10, 2010, 4:47:01 PM2/10/10
to
Kahuna, thanks for the suggestions!

I had tried most of them, but double checked to make sure. They all appear
to be correct except for the Manage Categories. There is no "Project
Manager" category. The only categories I have are: My Direct Reports, My
Organization, My Personal Projects, My Projects, My Resources and My Tasks.

Are there some default categories missing?

I tried adding a "Project Manager" category, adding the Administrators group
to it and giving it permssions but it didn't change anything. On the Add or
Edit Category page, there is a section for "Name and Description", "Users and
Groups", "Projects", "Resources", and "Views - Add to Category". In none of
these areas can I find a permission setting for "View Project Center".

Any other suggestions?

Thanks.

Gary Chefetz

unread,
Feb 11, 2010, 6:26:45 AM2/11/10
to
Jas:

Have you "Published" the projects? This is probably the most common error
new users make. You might want to have a look at our books at
https://projectserverbooks.com as doing this without good reference material
will eat up more time than you might have.

--
Gary L Chefetz, MVP, MCT, MCITP
msProjectExperts http://www.msprojectexperts.com
FAQs and Reference http://www.projectserverexperts.com
BLOG: http://projectserverhelp.com

"JasFr" <Ja...@discussions.microsoft.com> wrote in message
news:C0114CEF-07B5-4F62...@microsoft.com...

Piet Remen

unread,
Feb 11, 2010, 7:30:01 AM2/11/10
to
Howdy. Something sounds wrong in the view. Go to Server Settings>Manage
Views. Under the project center group, click on the view which is giving you
this message. Have a play with the settings on this page. One thing I know is
you will get this same message if you have a filter set that returns no data.
Click the filter button and make sure there is nothing here limiting the
results being shown in the project centre. The other thing is check the
security categories settings down the bottom of the page. Track it through to
check the category settings etc... Hopefully the problem is something to do
with this.

Regards,

Piet Remen
www.projectserver.com.au

JasFr

unread,
Feb 11, 2010, 9:00:02 AM2/11/10
to
Gary,

Thanks for the suggestion. I believe I mentioned in my initial post, but if
not yes I have published the projects. All of them were published through
Project Professional 2007 and they can all be seen on the server through the
web interface if I go to Server Settings-->Delete Enterprise Objects. They
won't show up in the Project Center though.

Thanks

JasFr

unread,
Feb 11, 2010, 9:05:02 AM2/11/10
to
Andrew,

Thanks for the reply. I'm with you in that it sounds like a security issue
but I can't for the life of me figure out what it is. As I said, I'm a
server admin, and a Project admin, my account was the admin listed when I
created the Project Web Access from the Shared Service Provider. And
finally, if I use the "View Effective Rights Tool" it shows me as having
rights on all of them.

As for having modified security permissions, I definitely have done some of
that in an attempt to get the projects to be viewable. As to what I've done,
I can't list it all but in every event it's been trying to make everything as
wide open as possible just to try and get the projects to show. In the
Manage Categories section though, I hadn't touched anything at all on the
default ones, I only added 2 categories.

And for the final question, I published all of the projects, so I assume
that makes me the Project Owner?

Thanks

"Andrew Lavinsky" wrote:

> .
>

JasFr

unread,
Feb 11, 2010, 9:07:02 AM2/11/10
to
Piet,

Thanks for the reply. I tried checking the view and there were no filters
set on it, all other settings look normal to me. In the Security Categories
section, I added all available categories just to try and that didn't help
either.

Thanks

Unknown

unread,
Feb 11, 2010, 9:24:26 AM2/11/10
to
Are you in multiple Groups? Try just putting your account in Admin and removing
it from any other Group that may provide a conflict. Check the My Organization
category assigned to Admin and make sure it contains that view and all projects
(not selected ones).

kahuna

unread,
Feb 11, 2010, 9:45:01 AM2/11/10
to
JasFr, one thing that helped me to figure out some permission issues was to
start off by giving full permissions on the Administrator User for Group,
Category, Security Template and Global and then one by one take out the
various options. Time consuming but it can work. Also, make sure that once
you are able to see all of it as an administrator, defining the Security
Templates for each profile (team member, project manager, executive and so
on), as it is much easier to then apply the templates to the Groups,
Category, User etc than do it individually.

Gary Chefetz

unread,
Feb 11, 2010, 2:22:07 PM2/11/10
to
Jas:

I saw that you wrote that you published them, but inasmuch as you say you're
new to Project Server, I can't be certain that you know what that means.
People use terms very loosely in the NGs. So forgive my skepticism, but I
still cant' be certain that you did this correctly given that you haven't
provided the steps you took.

So, I guess we'll have to go around again.

Did you use Tools > Enterprise Options > Import Project to Enterprise to
import the projects?
After importing, did you go to File > Open, open the project and the go to
File > Publish and publish the project?

If you can verify this, the only other explanation is that your security
setup is incorrect, regardless of what the effective rights tool tells you.

--
Gary L Chefetz, MVP, MCT, MCITP
msProjectExperts http://www.msprojectexperts.com
FAQs and Reference http://www.projectserverexperts.com
BLOG: http://projectserverhelp.com

"JasFr" <Ja...@discussions.microsoft.com> wrote in message

news:82C48534-0D3F-4E5A...@microsoft.com...

JasFr

unread,
Feb 11, 2010, 2:54:07 PM2/11/10
to
Gary,

You did it! I feel rather idiotic about that being the problem, but as I
said, I'm new to Project so I thought that "Export to Enterprise" was
actually publishing it and since they were showing up on the server in the
delete objects screen that made me think they were published.

Anyway, thanks a ton and thanks to everyone for all the suggestions.

Gary Chefetz

unread,
Feb 11, 2010, 4:15:58 PM2/11/10
to
Jas:

See, you could've had a V8! You also might take a look at two of the books
my partner Dale and I wrote. (Managing Enterprise Projects and Implementing
and Administering)They'll save you days and days of this kind of nonsense.
This is not an intuitive tool. Have a look at
http://www.projectserverbooks.com


--
Gary L Chefetz, MVP, MCT, MCITP
msProjectExperts http://www.msprojectexperts.com
FAQs and Reference http://www.projectserverexperts.com
BLOG: http://projectserverhelp.com

"JasFr" <Ja...@discussions.microsoft.com> wrote in message

news:6D979F39-1C91-4DEA...@microsoft.com...

JasFr

unread,
Feb 12, 2010, 9:10:01 AM2/12/10
to
Gary,

Thanks for the suggestion on the books. Next time we make a book order I'll
keep those in mind. I'm already feeling you on the non-intuitiveness of the
software as you can see heh. There also doesn't seem to be a lot of
troubleshooting content online about it.

Thanks again

Gary Chefetz

unread,
Feb 12, 2010, 5:11:43 PM2/12/10
to
On our Projectserverexperts.com site, we have a listing of all the best
blogs for Project Server. You'll want to pay close attention to the
Microsoft bloggers, in particular, Christophe Fiessinger and Brian Smith are
very prolific and most often first-to-market with important advice and
updates from Microsoft. Eventually you can find everything in the KB or in
TechNet, which is a very good, and growing-better-by-the-day source of
information. Then you have MVPs many of whom maintain sites and blogs as
well as many other "Projectserverati" who generate great content as well. Of
course these newsgroups are a wonderful support pillar. There's lots of info
out there, you simply need to tune into all the different channels.

--
Gary L Chefetz, MVP, MCT, MCITP
msProjectExperts http://www.msprojectexperts.com
FAQs and Reference http://www.projectserverexperts.com
BLOG: http://projectserverhelp.com

"JasFr" <Ja...@discussions.microsoft.com> wrote in message

news:4548FD71-FD13-4CB4...@microsoft.com...

Fleur Jeanne

unread,
Aug 3, 2010, 9:10:35 PM8/3/10
to
Hi Gary,

I ve got same issue than jas, and i checked all your posts and did what you said but the project is still not showing on project center even if i published it, checked all the security but it appear under"Delete Enterprise Objects ".
Please help me. I m struggling since few days now.
thanks a lot

Fleur

Gary Chefetz wrote:

Jas:I saw that you wrote that you published them, but inasmuch as you say you

11-Feb-10

Jas:

I saw that you wrote that you published them, but inasmuch as you say you are
new to Project Server, I cannot be certain that you know what that means.


People use terms very loosely in the NGs. So forgive my skepticism, but I

still cant' be certain that you did this correctly given that you have not


provided the steps you took.

So, I guess we will have to go around again.

Did you use Tools > Enterprise Options > Import Project to Enterprise to
import the projects?
After importing, did you go to File > Open, open the project and the go to
File > Publish and publish the project?

If you can verify this, the only other explanation is that your security
setup is incorrect, regardless of what the effective rights tool tells you.

--
Gary L Chefetz, MVP, MCT, MCITP
msProjectExperts http://www.msprojectexperts.com
FAQs and Reference http://www.projectserverexperts.com
BLOG: http://projectserverhelp.com

Previous Posts In This Thread:

On Wednesday, February 10, 2010 3:27 PM
JasFr wrote:

Can't view projects in Project Center
Hello, still new to Project and learning plenty. I have managed to get Project


Web Access up and running, synch A.D. users and upload projects.

Problem: I cannot view (literally, they do not appear in the Project Center"


area) any of the published projects. I am able to view all resources,
including those that were added during publishing.

When I go to Project Center, I get this message:
"There are no projects to view in Project Center. This is because you might
not have permissions on any projects or no projects are published."

I am a local admin on the server and an administrator in Project Web Access.
I am also have rights on all 4 Project databases.

When I go to Server Settings --> Delete Enterprise Objects all of the
projects show up in the list of deletable projects. Also, if I try to open
the projects from the server using Project Professional 2007 they appear and
open fine.

I have tried using the View Effective Rights Tool for 2007 on the server and
it shows me as having permission for any project I check.

Is there anything that I need to do after uploading a project from Project
Professional 2007 to a default installation of Project Web Access? Event the

simplest thing could help, I am open to anything really as I have tried


everything I can think of.

Thanks for any help!

On Wednesday, February 10, 2010 4:23 PM
kahuna wrote:

JasFR - I believe you could tray a few things...
JasFR - I believe you could tray a few things... First, could you check
Server>Security> Project Web Access Permissions page to see if global
permissions are set up to view projects in the project center. Also, ensure
the same is granted in the Security Templates page for Administrators, which
you can then use on the Project Manager category under Manage Categories. And
finally, you can check your user permissions under Manage Users and ensure
the same is set up.

"JasFr" wrote:

On Wednesday, February 10, 2010 4:31 PM
Andrew Lavinsky wrote:

Gotta be a security issue - unless you somehow added filters to the
Gotta be a security issue - unless you somehow added filters to the views

without realizing it. My guess is that it is a Category issue. Are you using


default security permissions, or have you modified them in any way. If you
have modified them, then how did you do so?

Does the project owner have the same issue for their own projects? (or are
you the project owner)

On Wednesday, February 10, 2010 4:47 PM
JasFr wrote:

Kahuna, thanks for the suggestions!
Kahuna, thanks for the suggestions!

I had tried most of them, but double checked to make sure. They all appear
to be correct except for the Manage Categories. There is no "Project
Manager" category. The only categories I have are: My Direct Reports, My
Organization, My Personal Projects, My Projects, My Resources and My Tasks.

Are there isome default categories missing?

I tried adding a "Project Manager" category, adding the Administrators group

to it and giving it permssions but it did not change anything. On the Add or


Edit Category page, there is a section for "Name and Description", "Users and
Groups", "Projects", "Resources", and "Views - Add to Category". In none of
these areas can I find a permission setting for "View Project Center".

Any other suggestions?

Thanks.
"kahuna" wrote:

On Thursday, February 11, 2010 6:26 AM
Gary Chefetz wrote:

Jas:Have you "Published" the projects?
Jas:

Have you "Published" the projects? This is probably the most common error
new users make. You might want to have a look at our books at
https://projectserverbooks.com as doing this without good reference material
will eat up more time than you might have.

--
Gary L Chefetz, MVP, MCT, MCITP
msProjectExperts http://www.msprojectexperts.com
FAQs and Reference http://www.projectserverexperts.com
BLOG: http://projectserverhelp.com

On Thursday, February 11, 2010 7:30 AM
Piet Remen wrote:

Howdy. Something sounds wrong in the view. Go to Server Settings>ManageViews.
Howdy. Something sounds wrong in the view. Go to Server Settings>Manage
Views. Under the project center group, click on the view which is giving you
this message. Have a play with the settings on this page. One thing I know is
you will get this same message if you have a filter set that returns no data.
Click the filter button and make sure there is nothing here limiting the
results being shown in the project centre. The other thing is check the
security categories settings down the bottom of the page. Track it through to
check the category settings etc... Hopefully the problem is something to do
with this.

Regards,

Piet Remen
www.projectserver.com.au

On Thursday, February 11, 2010 9:00 AM
JasFr wrote:

Gary,Thanks for the suggestion.
Gary,

Thanks for the suggestion. I believe I mentioned in my initial post, but if
not yes I have published the projects. All of them were published through
Project Professional 2007 and they can all be seen on the server through the
web interface if I go to Server Settings-->Delete Enterprise Objects. They

will not show up in the Project Center though.

Thanks

"Gary Chefetz" wrote:

On Thursday, February 11, 2010 9:05 AM
JasFr wrote:

Andrew,Thanks for the reply.
Andrew,

Thanks for the reply. I am with you in that it sounds like a security issue
but I cannot for the life of me figure out what it is. As I said, I am a


server admin, and a Project admin, my account was the admin listed when I
created the Project Web Access from the Shared Service Provider. And

finally, if I use the "View Effective Rights Tool" it shows me as having


rights on all of them.

As for having modified security permissions, I definitely have done some of

that in an attempt to get the projects to be viewable. As to what I have done,
I cannot list it all but in every event it is been trying to make everything as


wide open as possible just to try and get the projects to show. In the

Manage Categories section though, I had not touched anything at all on the


default ones, I only added 2 categories.

And for the final question, I published all of the projects, so I assume
that makes me the Project Owner?

Thanks

"Andrew Lavinsky" wrote:

On Thursday, February 11, 2010 9:07 AM
JasFr wrote:

Piet,Thanks for the reply.
Piet,

Thanks for the reply. I tried checking the view and there were no filters
set on it, all other settings look normal to me. In the Security Categories

section, I added all available categories just to try and that did not help
either.

Thanks

"Piet Remen" wrote:

On Thursday, February 11, 2010 9:45 AM
kahuna wrote:

JasFr, one thing that helped me to figure out some permission issues was
JasFr, one thing that helped me to figure out some permission issues was to
start off by giving full permissions on the Administrator User for Group,
Category, Security Template and Global and then one by one take out the
various options. Time consuming but it can work. Also, make sure that once
you are able to see all of it as an administrator, defining the Security
Templates for each profile (team member, project manager, executive and so
on), as it is much easier to then apply the templates to the Groups,
Category, User etc than do it individually.

"JasFr" wrote:

On Thursday, February 11, 2010 2:22 PM
Gary Chefetz wrote:

Jas:I saw that you wrote that you published them, but inasmuch as you say you
Jas:

I saw that you wrote that you published them, but inasmuch as you say you are
new to Project Server, I cannot be certain that you know what that means.


People use terms very loosely in the NGs. So forgive my skepticism, but I

still cant' be certain that you did this correctly given that you have not


provided the steps you took.

So, I guess we will have to go around again.

Did you use Tools > Enterprise Options > Import Project to Enterprise to
import the projects?
After importing, did you go to File > Open, open the project and the go to
File > Publish and publish the project?

If you can verify this, the only other explanation is that your security
setup is incorrect, regardless of what the effective rights tool tells you.

--
Gary L Chefetz, MVP, MCT, MCITP
msProjectExperts http://www.msprojectexperts.com
FAQs and Reference http://www.projectserverexperts.com
BLOG: http://projectserverhelp.com

On Thursday, February 11, 2010 2:54 PM
JasFr wrote:

Gary,You did it!
Gary,

You did it! I feel rather idiotic about that being the problem, but as I

said, I am new to Project so I thought that "Export to Enterprise" was


actually publishing it and since they were showing up on the server in the
delete objects screen that made me think they were published.

Anyway, thanks a ton and thanks to everyone for all the suggestions.

"Gary Chefetz" wrote:

On Thursday, February 11, 2010 4:15 PM
Gary Chefetz wrote:

Jas:See, you could have had a V8!
Jas:

See, you could have had a V8! You also might take a look at two of the books


my partner Dale and I wrote. (Managing Enterprise Projects and Implementing
and Administering)They'll save you days and days of this kind of nonsense.
This is not an intuitive tool. Have a look at
http://www.projectserverbooks.com

--
Gary L Chefetz, MVP, MCT, MCITP
msProjectExperts http://www.msprojectexperts.com
FAQs and Reference http://www.projectserverexperts.com
BLOG: http://projectserverhelp.com

On Friday, February 12, 2010 9:10 AM
JasFr wrote:

Gary,Thanks for the suggestion on the books.
Gary,

Thanks for the suggestion on the books. Next time we make a book order I will
keep those in mind. I am already feeling you on the non-intuitiveness of the
software as you can see heh. There also does not seem to be a lot of


troubleshooting content online about it.

Thanks again

"Gary Chefetz" wrote:

On Friday, February 12, 2010 5:11 PM
Gary Chefetz wrote:

On our Projectserverexperts.


On our Projectserverexperts.com site, we have a listing of all the best
blogs for Project Server. You'll want to pay close attention to the
Microsoft bloggers, in particular, Christophe Fiessinger and Brian Smith are
very prolific and most often first-to-market with important advice and
updates from Microsoft. Eventually you can find everything in the KB or in
TechNet, which is a very good, and growing-better-by-the-day source of
information. Then you have MVPs many of whom maintain sites and blogs as
well as many other "Projectserverati" who generate great content as well. Of

course these newsgroups are a wonderful support pillar. There is lots of info


out there, you simply need to tune into all the different channels.

--


Gary L Chefetz, MVP, MCT, MCITP
msProjectExperts http://www.msprojectexperts.com
FAQs and Reference http://www.projectserverexperts.com
BLOG: http://projectserverhelp.com


Submitted via EggHeadCafe - Software Developer Portal of Choice
Make The WebClient Class follow redirects and get Target Url
http://www.eggheadcafe.com/tutorials/aspnet/70511872-c3aa-4e92-a7d7-dd4b09881af5/make-the-webclient-class-follow-redirects-and-get-target-url.aspx

Fleur Jeanne

unread,
Aug 3, 2010, 9:55:03 PM8/3/10
to
hi gary,

i ve got the same issue than jas and i ve followed and published your advices. but i still can t see any of my project in project center
please help me

fleur

Gary Chefetz wrote:

Jas:I saw that you wrote that you published them, but inasmuch as you say you

11-Feb-10

Jas:

I saw that you wrote that you published them, but inasmuch as you say you are
new to Project Server, I cannot be certain that you know what that means.


People use terms very loosely in the NGs. So forgive my skepticism, but I

still cant' be certain that you did this correctly given that you have not


provided the steps you took.

So, I guess we will have to go around again.

Did you use Tools > Enterprise Options > Import Project to Enterprise to
import the projects?
After importing, did you go to File > Open, open the project and the go to
File > Publish and publish the project?

If you can verify this, the only other explanation is that your security
setup is incorrect, regardless of what the effective rights tool tells you.

--
Gary L Chefetz, MVP, MCT, MCITP
msProjectExperts http://www.msprojectexperts.com
FAQs and Reference http://www.projectserverexperts.com
BLOG: http://projectserverhelp.com

Previous Posts In This Thread:

On Wednesday, February 10, 2010 3:27 PM
JasFr wrote:

Can't view projects in Project Center

Hello, still new to Project and learning plenty. I have managed to get Project


Web Access up and running, synch A.D. users and upload projects.

Problem: I cannot view (literally, they do not appear in the Project Center"


area) any of the published projects. I am able to view all resources,
including those that were added during publishing.

When I go to Project Center, I get this message:
"There are no projects to view in Project Center. This is because you might
not have permissions on any projects or no projects are published."

I am a local admin on the server and an administrator in Project Web Access.
I am also have rights on all 4 Project databases.

When I go to Server Settings --> Delete Enterprise Objects all of the
projects show up in the list of deletable projects. Also, if I try to open
the projects from the server using Project Professional 2007 they appear and
open fine.

I have tried using the View Effective Rights Tool for 2007 on the server and
it shows me as having permission for any project I check.

Is there anything that I need to do after uploading a project from Project
Professional 2007 to a default installation of Project Web Access? Event the

simplest thing could help, I am open to anything really as I have tried


everything I can think of.

Thanks for any help!

On Wednesday, February 10, 2010 4:23 PM
kahuna wrote:

JasFR - I believe you could tray a few things...
JasFR - I believe you could tray a few things... First, could you check
Server>Security> Project Web Access Permissions page to see if global
permissions are set up to view projects in the project center. Also, ensure
the same is granted in the Security Templates page for Administrators, which
you can then use on the Project Manager category under Manage Categories. And
finally, you can check your user permissions under Manage Users and ensure
the same is set up.

"JasFr" wrote:

On Wednesday, February 10, 2010 4:31 PM
Andrew Lavinsky wrote:

Gotta be a security issue - unless you somehow added filters to the
Gotta be a security issue - unless you somehow added filters to the views
without realizing it. My guess is that it is a Category issue. Are you using
default security permissions, or have you modified them in any way. If you
have modified them, then how did you do so?

Does the project owner have the same issue for their own projects? (or are
you the project owner)

On Wednesday, February 10, 2010 4:47 PM
JasFr wrote:

Kahuna, thanks for the suggestions!
Kahuna, thanks for the suggestions!

I had tried most of them, but double checked to make sure. They all appear
to be correct except for the Manage Categories. There is no "Project
Manager" category. The only categories I have are: My Direct Reports, My
Organization, My Personal Projects, My Projects, My Resources and My Tasks.

Are there isome default categories missing?

I tried adding a "Project Manager" category, adding the Administrators group

to it and giving it permssions but it did not change anything. On the Add or


Edit Category page, there is a section for "Name and Description", "Users and
Groups", "Projects", "Resources", and "Views - Add to Category". In none of
these areas can I find a permission setting for "View Project Center".

Any other suggestions?

Thanks.
"kahuna" wrote:

On Thursday, February 11, 2010 6:26 AM

Gary Chefetz wrote:

Jas:Have you "Published" the projects?
Jas:

Have you "Published" the projects? This is probably the most common error
new users make. You might want to have a look at our books at
https://projectserverbooks.com as doing this without good reference material
will eat up more time than you might have.

--
Gary L Chefetz, MVP, MCT, MCITP
msProjectExperts http://www.msprojectexperts.com
FAQs and Reference http://www.projectserverexperts.com
BLOG: http://projectserverhelp.com

On Thursday, February 11, 2010 7:30 AM
Piet Remen wrote:

Howdy. Something sounds wrong in the view. Go to Server Settings>ManageViews.
Howdy. Something sounds wrong in the view. Go to Server Settings>Manage
Views. Under the project center group, click on the view which is giving you
this message. Have a play with the settings on this page. One thing I know is
you will get this same message if you have a filter set that returns no data.
Click the filter button and make sure there is nothing here limiting the
results being shown in the project centre. The other thing is check the
security categories settings down the bottom of the page. Track it through to
check the category settings etc... Hopefully the problem is something to do
with this.

Regards,

Piet Remen
www.projectserver.com.au

On Thursday, February 11, 2010 9:00 AM
JasFr wrote:

Gary,Thanks for the suggestion.
Gary,

Thanks for the suggestion. I believe I mentioned in my initial post, but if
not yes I have published the projects. All of them were published through
Project Professional 2007 and they can all be seen on the server through the
web interface if I go to Server Settings-->Delete Enterprise Objects. They

will not show up in the Project Center though.

Thanks

"Gary Chefetz" wrote:

Thanks

"Andrew Lavinsky" wrote:

Thanks

"Piet Remen" wrote:

"JasFr" wrote:

Jas:I saw that you wrote that you published them, but inasmuch as you say you
Jas:

I saw that you wrote that you published them, but inasmuch as you say you are
new to Project Server, I cannot be certain that you know what that means.


People use terms very loosely in the NGs. So forgive my skepticism, but I

still cant' be certain that you did this correctly given that you have not


provided the steps you took.

So, I guess we will have to go around again.

Did you use Tools > Enterprise Options > Import Project to Enterprise to
import the projects?
After importing, did you go to File > Open, open the project and the go to
File > Publish and publish the project?

If you can verify this, the only other explanation is that your security
setup is incorrect, regardless of what the effective rights tool tells you.

--
Gary L Chefetz, MVP, MCT, MCITP
msProjectExperts http://www.msprojectexperts.com
FAQs and Reference http://www.projectserverexperts.com
BLOG: http://projectserverhelp.com

On Thursday, February 11, 2010 2:54 PM
JasFr wrote:

Gary,You did it!
Gary,

You did it! I feel rather idiotic about that being the problem, but as I
said, I am new to Project so I thought that "Export to Enterprise" was
actually publishing it and since they were showing up on the server in the
delete objects screen that made me think they were published.

Anyway, thanks a ton and thanks to everyone for all the suggestions.

"Gary Chefetz" wrote:

On Thursday, February 11, 2010 4:15 PM
Gary Chefetz wrote:

Jas:See, you could have had a V8!
Jas:

See, you could have had a V8! You also might take a look at two of the books
my partner Dale and I wrote. (Managing Enterprise Projects and Implementing
and Administering)They'll save you days and days of this kind of nonsense.
This is not an intuitive tool. Have a look at
http://www.projectserverbooks.com

--
Gary L Chefetz, MVP, MCT, MCITP
msProjectExperts http://www.msprojectexperts.com
FAQs and Reference http://www.projectserverexperts.com
BLOG: http://projectserverhelp.com

On Friday, February 12, 2010 9:10 AM
JasFr wrote:

Gary,Thanks for the suggestion on the books.
Gary,

Thanks for the suggestion on the books. Next time we make a book order I will
keep those in mind. I am already feeling you on the non-intuitiveness of the
software as you can see heh. There also does not seem to be a lot of
troubleshooting content online about it.

Thanks again

"Gary Chefetz" wrote:

On Friday, February 12, 2010 5:11 PM
Gary Chefetz wrote:

On our Projectserverexperts.
On our Projectserverexperts.com site, we have a listing of all the best
blogs for Project Server. You'll want to pay close attention to the
Microsoft bloggers, in particular, Christophe Fiessinger and Brian Smith are
very prolific and most often first-to-market with important advice and
updates from Microsoft. Eventually you can find everything in the KB or in
TechNet, which is a very good, and growing-better-by-the-day source of
information. Then you have MVPs many of whom maintain sites and blogs as
well as many other "Projectserverati" who generate great content as well. Of
course these newsgroups are a wonderful support pillar. There is lots of info
out there, you simply need to tune into all the different channels.

--


Gary L Chefetz, MVP, MCT, MCITP
msProjectExperts http://www.msprojectexperts.com
FAQs and Reference http://www.projectserverexperts.com
BLOG: http://projectserverhelp.com

On Tuesday, August 03, 2010 9:10 PM
Fleur Jeanne wrote:

same issue than jas
Hi Gary,

I ve got same issue than jas, and i checked all your posts and did what you said but the project is still not showing on project center even if i published it, checked all the security but it appear under"Delete Enterprise Objects ".
Please help me. I m struggling since few days now.
thanks a lot

Fleur


Submitted via EggHeadCafe - Software Developer Portal of Choice

Custom Favorites Web Site with MongoDb and NoRM
http://www.eggheadcafe.com/tutorials/aspnet/7fbc7a01-5d30-4cd3-b373-51d4a0e1afa8/custom-favorites-web-site-with-mongodb-and-norm.aspx

Chris Davis

unread,
Aug 16, 2010, 9:08:57 AM8/16/10
to
Hi Fleur,

One additional thing to try (which was my problem, is mentioned above but perhaps not that easy to follow) is to go to server settings > Manage Categories. Click on the category your projects were created under (in my case My Organisation) then click on the group your user is a member of in the right hand drop down.) This will bring up the permissions for that group in that category. In my case the user had global permissions, was a member of My Organisation but still could not see the projects due to no permissions being set here...

Submitted via EggHeadCafe - Software Developer Portal of Choice

ASP.NET Providerless Custom Forms Authentication, Roles and Profile with MongoDb
http://www.eggheadcafe.com/tutorials/aspnet/27f836b7-2c9e-4942-9712-1c7b901cadcc/aspnet-providerless-custom-forms-authentication-roles-and-profile-with-mongodb.aspx

0 new messages