What you want to do in a Project Details view in PWA cannot be done. In the
Tracking Gantt view in Microsoft Project 2007, you can see the progress
information shown on summary tasks and the Project Summary Task, shown as a
"fence post" or "teeth" pattern on the summary task's Gantt bar. In PWA,
however, you can only show progress on regular tasks. You cannot show
progress on summary task Gantt bars, such as in a Project Details view.
Hope this helps.
--