Actuals entered in project file does not show in PWA

0 views
Skip to first unread message

Ben

unread,
Mar 30, 2010, 11:27:01 AM3/30/10
to
Hi, when actuals are entered in MS Project 2003 using the Task usage view,
they do not appear in PWA. So a resource enters new actuals using PWA, all
actuals previously entered from MS Project are deleted.

Is there a way to have previously entered actuals with MSP shown in PWA?

Thanks!

Unknown

unread,
Mar 30, 2010, 11:45:02 AM3/30/10
to
Are you publishing the changes after they've been entered in MS Project?

- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm

Gary L. Chefetz

unread,
Mar 30, 2010, 12:19:22 PM3/30/10
to
Ben:

Using 2003, you need to "Republish" tasks that you status in Project
directly selecting the option to "overwrite actual work" in PWA. This is the
only way to get the actual work entered in Project to show up in PWA. Using
Publish only, will not do the trick.

--
Gary L. Chefetz, MVP, MCT, MCTIP
Business: http://www.msprojectexperts.com
FAQs: http://www.projectserverexperts.com
BLOG: http://www.projectserverhelp.com

"Ben" <B...@discussions.microsoft.com> wrote in message
news:2ADAA87C-87A5-4033...@microsoft.com...

Ben

unread,
Mar 30, 2010, 2:02:01 PM3/30/10
to
Thanks for the information, but where do you select the "overwrite actual
work" option?

Ben

unread,
Mar 30, 2010, 3:01:01 PM3/30/10
to
OK! Found it!

Thanks again!