Re: Enterprise Project Text field does not show up in the project web.

0 views
Skip to first unread message

Dale Howard [MVP] dot at dot

unread,
Nov 4, 2004, 10:57:12 AM11/4/04
to
Where?

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
"We wrote the book on Project Server"


"NW" <N...@discussions.microsoft.com> wrote in message
news:4918B37A-2A25-4517...@microsoft.com...
>


NW

unread,
Nov 4, 2004, 11:14:03 AM11/4/04
to
It actually cut out the rest of the subject line....

Enterprise Project Text field does not show up in the project web access
project center edit fields. Actually, out of the four only three show up and
not the fourth one. "Enterprise Project Text1" does not show up.

Also, none of the Number fields show up as well.

Thanks.

Dale Howard [MVP] dot at

unread,
Nov 5, 2004, 12:56:22 PM11/5/04
to
NW --

When you select a project in the Project Center and then click the Edit
button, the Project Details page displays all custom enterprise Project
outline
codes currently in use, plus only those enterprise Project fields that do
not contain either a value list or a formula. By chance, does your
Entperprise Project Text1 field contain a value list? And do your
Enterprise Project Number fields contain formulas?

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant

Denver, Colorado


http://www.msprojectexperts.com
"We wrote the book on Project Server"


"NW" <N...@discussions.microsoft.com> wrote in message

news:F97CC8FF-6413-4187...@microsoft.com...