ProjectServerViewOlapDataRole'

63 views
Skip to first unread message

opmanager

unread,
Jan 4, 2008, 12:21:48 PM1/4/08
to
Hi,

When I try to build cube on project website I get this below mentioned
error.Can anyone help me in resolving this.

3 of the NT accounts that correspond to users that have 'View Olap Data'
permission could not be added to the Project Server default OLAP role
'ProjectServerViewOlapDataRole'

Thanks in advance.

Ravi


Mike Glen

unread,
Jan 14, 2008, 9:03:19 AM1/14/08
to
Hi Ravi,

Try posting on the server newsgroup as this one is closing down. Please see
FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful
Project information can be seen at this web
address:http://project.mvps.org/faqs.htm .

Mike Glen
Project MVP

"opmanager" <opma...@wellinx.com> wrote in message
news:OGpyLZvT...@TK2MSFTNGP04.phx.gbl...

PJ Mistry

unread,
Jan 24, 2008, 11:41:28 AM1/24/08
to
Hi Ravi;

During the cube generation we try to add all the users that have an NT
account and have the permission "View Olap Data" to the
"ProjectServerViewOlapRole". If some of these users have an incorrect (or
maybe no longer valid) NT account specified we will fail to add them to
"ProjectServerViewOlapRole". For example, if 2 Form based authentication
users have "View Olap Data" permission, you will see the following warning
message during cube building process:

"2 of the NT accounts that correspond to users that have 'View Olap Data'

permission could not be added to the Project Server default OLAP role
'ProjectServerViewOlapDataRole'"

This is just a warning message, the cube build process will finally go
successfully (log: Cube build request completed successfully).

Hope this helps.

Thanks

Regards
PJ Mistry