>The cell is formated to h:mm
When I do a control and click on the both of the weekly
totals, it shows 80 hours (for 2 weeks) on the status bar
below but on the in the cell on the spreadsheet it still
shows 16:00
Louis
You must custom format the cell as [h]:mm. The [] tells
Excel to roll over the hours (past 24:00). Format > Cells
> Number tab, click Custom, and insert [h]:mm on the right
underneath "Type".
Jason
--