Summary Tasks and Percentage Required

4 views
Skip to first unread message

dushu

unread,
Jun 20, 2007, 4:49:31 AM6/20/07
to microsoft project
I have set-up a schedule with many tasks and summary tasks with
resources and everything. While tracking the project I set the
percentages for the individual tasks - and microsoft project
automatically assigns the percentage complete to the summary tasks.
My
question is:

1) How does MSP calculate the percentage for the summary task -
Summary Tasks do not seem to show the percentage complete accurately.
The individual tasks all have the required percentage complete - but
the summary taks either shows delay (and in some cases ahead of
shedule) Please see screenshot at


http://www.ccaalumni.org/Summary.jpg


2) Where can I get a percentage required as per the baseline for each
task ?


Regards,
Dushyant Ahuja