The problem that I am having is that Microsoft Project is not
restricting the resource by saying that they can ONLY work 20% of their
time on this project so if there are tasks that add up to greater than
20% of their time then they will be delayed.
Is there any easy way to do this in Project? Do I have to individually
change the percentage of work that they are doing to fit the overall
20%?
Thanks.