> Hi Guys,
> Thanks for the support as I'm new with Merlin but a long time user of
> OmniPlan.
>
> In my business we don't put as much emphasis on resources or effort in
> the planning stage, mainly just duration as we pull in the resources/
> staff necessary to complete each task/activity and often give
> ourselves a week duration to finish a 4 hour task.
>
> After a lot of testing and reading the help file I think the best
> column for me to use (out of the many, many columns dedicated to
> DURATION) is "Given Planned Duration". This seems closest to
> OmniPlan's "Duration" column. Am I correct? On the fly I need a quick
> column that I can change based on feedback from my team how long each
> activity is going to and/or should take.
>
> I aslo don't want to see that column convert everything to hours as I
> don't get down to the granularity and just want things in working days
> or weeks (not calendar).
>
> So in summary:
>
> 1. Is Given Planned Duration the best column for me to quickly update
> how long in working days each task/activity is going to take?
"Given Planned Duration" defines the planned duration for the task during planning. If the works on a task should have a fix duration no matter how many resources are assigned or not, you may enter this time in the "given planned duration". Yes.
To update the overall duration of a task (because the works on this task had been started and are in progress) you edit the actuals.
You can use the "actuals" tab or actual columns. So if the actual duration changes as soon as work takes place, you update the task in absolute mode, enter the amount of work performed in the task and the remaining amount of work.
all editable columns with time units, are using custom time units. So if you type in "1 m" it will be 1 month. If you type 14 d it will be 14 days and so on. So these values will stay in the way you typed them in. Please also observe that we have two values for duration. The duration which is calculated on working time in the project (means the days you work f.ex. mondays to fridays) (1day is usually 8 hours of working time) or the elapsed duration which is our time (24h are 1 day). So if you type in 14 d it will be 14 days of working time. If you type in 14 ed it will be 14 elapsed days, which is 14 days with 24hours.
Coming back to your question. I would activate the expected column, so you can see you planned values for duration in the "Given Planned Duration" column and next to it I would use the "Expected Duration" column. Which uses the units you can set in the Project Settings.
I hope this helps you a little bit to understand how Merlin handles the times.
Thanks.
Antoni
> --
> You received this message because you are subscribed to the Google Groups "Merlin2Users" group.
> To post to this group, send email to merlin...@googlegroups.com.
> To unsubscribe from this group, send email to merlin2users...@googlegroups.com.
> For more options, visit this group at http://groups.google.com/group/merlin2users?hl=en.
>
>