Ashwani Thakur

unread,
Mar 16, 2013, 6:56:49 AM3/16/13
to megapo...@googlegroups.com
Friends,

I spoke to Kumar builder representative today and i am told that E-building possession would be given in month of Jun 2014.

In my agreement they had committed for 48th months period from the date of commencement of construction.

In my agreement this date is 02-02-2009 which means 48 month are already over.

This is really being delayed.

Can we do something in this regard?

Thanks
Ashwani

E-1204

9881120823

anil rao

unread,
Mar 16, 2013, 7:46:10 AM3/16/13
to megapo...@googlegroups.com

I spoke to Mega from kumar builders office. She told me for sangria E. Tower the possession is December 2013.

I still don't understand why they are collecting money every month.

I am writing a letter to them now.

Cheers.
Anil 

--
--
You received this message because you are subscribed to the Google
Groups "megapolispune" group.
To post to this group, send email to megapo...@googlegroups.com
To unsubscribe from this group, send email to
megapolispun...@googlegroups.com
For more options, visit this group at
http://groups.google.com/group/megapolispune?hl=en
 
---
You received this message because you are subscribed to the Google Groups "megapolispune" group.
To unsubscribe from this group and stop receiving emails from it, send an email to megapolispun...@googlegroups.com.
For more options, visit https://groups.google.com/groups/opt_out.
 
 

anil rao

unread,
Mar 16, 2013, 7:47:05 AM3/16/13
to megapo...@googlegroups.com

Its not Mega, its Neha Karwa .

Shirish Dhamnekar

unread,
Mar 16, 2013, 11:38:45 AM3/16/13
to megapo...@googlegroups.com
Thanks for update. I think we should go and meet Mr. Hemant Kulkarni - Vice president Marketing as a group.
 
If we discuss collectively with Megapolis it might have some impact.
 
Warm regards,
Shirish Dhamnekar
 

 

Date: Sat, 16 Mar 2013 17:17:05 +0530
Subject: Re: [MegaPolis] Sangria Cluster
From: anil.f...@gmail.com
To: megapo...@googlegroups.com

MegaPolis Pune

unread,
Mar 17, 2013, 5:48:26 AM3/17/13
to megapo...@googlegroups.com
I agree we should form an active group and follow with Builder on this...

How many other people are getting these emails??

It would be great if we know how many folks are active...

Thanks
Ashwani

Ashutosh Singh

unread,
Jul 22, 2013, 6:46:56 AM7/22/13
to megapo...@googlegroups.com
 
 22 Slabs Completed .. I dont think it will go beyond March 2013

anil rao

unread,
Jul 22, 2013, 9:16:54 PM7/22/13
to megapo...@googlegroups.com

I have been told that the possession will be given in Jan 2014. what can anybody do about it?

--
--
You received this message because you are subscribed to the Google
Groups "megapolispune" group.
To post to this group, send email to megapo...@googlegroups.com
 
For more options, visit this group at
http://groups.google.com/group/megapolispune?hl=en
---
You received this message because you are subscribed to the Google Groups "megapolispune" group.
To post to this group, send email to megapo...@googlegroups.com.
Visit this group at http://groups.google.com/group/megapolispune.
 
 

vikzz vikz

unread,
Jul 23, 2013, 5:13:46 AM7/23/13
to megapo...@googlegroups.com

Stop all payments to the builder

anil rao

unread,
Jul 23, 2013, 9:05:22 AM7/23/13
to megapo...@googlegroups.com

That I have already done. but they are going to fine us you know that.

vikzz vikz

unread,
Jul 23, 2013, 9:10:42 AM7/23/13
to megapo...@googlegroups.com

No one fines me if its not my fault....i  have made it clear to them

anil rao

unread,
Jul 23, 2013, 11:01:39 AM7/23/13
to megapo...@googlegroups.com

Have they agreed?