Re: Mayflower/ Pls. resolve all pending Issues before final hand-over.

9 views
Skip to first unread message

Sanjay....@relianceada.com

unread,
Feb 24, 2009, 6:03:12 AM2/24/09
to Meera Bharti, Cm Mate, Mayflo...@googlegroups.com, Mayflower Mgc, Anil Nambiar, P Premchandran, Chandra...@relianceada.com, m.sa...@tcs.com, manoj....@gmail.com, S.Srin...@ticb.com, trid...@hotmail.com, xavier...@yahoo.com, rpriy...@yahoo.co.in, sushi...@ril.com

1.        We discussed on this matter on 18th Feb.
2.        Almost all the services are already taken over and being maintained by us except some technical support in maintaining the Electro-Mech. items.
3.        Our below issues, which are repeatedly raised to you and your other concerned colleagues are still OPEN and need your kind support in getting them closed on fast track before a final hand-over.
3.1         Reference our letter Ref: LH-0608/01 dtd. 17th June 2008. Action against all the 18 nos. Punch points are still OPEN.
3.2         Society Conveyance Deed is pending?
3.3         We have not yet received the TMC Approved Plan as well as Property demarcation Layout of Mayflower. Kindly provide the same.
3.4        M/s Hiranandani Approval on the proposed Plan for main Entry & Exit of ButterCup Vehicles.
4.        Final Cut-off date of hand-over should be fixed in accordance to closure date of above pending issues, which are critical for the smooth maintenance of Mayflower society by the committee.
5.        We would insist for a formal hand-over and takeover exercise, which may be duly signed by your project in charge as well as our society representative.

Looking for an excellent customer support from you.

Thanks&Regards...............SKG
2CA04, C-Block, 2nd Floor,
DAKC.

Direct: +91 22 303 82104
RIM: +91 9322598171



"Meera Bharti" <bharat...@hiranandani.net>

02/24/2009 11:08 AM

       
        To:        "Anil Nambiar" <nambia...@hiranandani.net>, "P Premchandran" <p.premc...@hiranandani.net>, "Cm Mate" <mat...@hiranandani.net>
        cc:        <Sanjay....@relianceada.com>, "Mayflower Mgc" <mayflo...@gmail.com>, <Mayflo...@googlegroups.com>
        Subject:        Mayflower
 Importance: Normal Sender's OU: Reliance



Mr. Nambiar
 
Please hand over all the remaining services of the Mayflower building to the committee on 1st March, 2009. Please give them necessary information about the vendors and the service providers, along with all the AMCs.
 
Regards
 
Meera Bharati
B.Com. A.C.A.
DGM-Finance
Hiranandani Group

Disclaimer: The information contained in this mail and any attachment hereof may be Confidential, privileged, propriety or otherwise protected from disclosure. If the reader of this message is not the intended recipient, you are hereby notified that any dissemination, distribution, copying or use of this message and any attachment is strictly prohibited. If you have received this message in error, please notify us immediately by replying to the message and permanently deleting it from your computer and destroying any printout thereof.




The information contained in this e-mail message is intended only for the use of the individual or entity to which it is addressed. If you are not the intended recipient, you should return it to the sender immediately. Please note that while we scan all e-mails for viruses we cannot guarantee that any e-mail is virus-free and accept no liability for any damage caused by any virus transmitted by this email.

Sanjay....@relianceada.com

unread,
Feb 25, 2009, 12:38:42 AM2/25/09
to Meera Bharti, Chandra...@relianceada.com, manoj....@gmail.com, Cm Mate, Mayflo...@googlegroups.com, MayflowerMgc, m.sa...@tcs.com, Anil Nambiar, P Premchandran, rpriy...@yahoo.co.in, sushi...@ril.com, S.Srin...@ticb.com, trid...@hotmail.com, xavier...@yahoo.com

It is perfectly OK to us. Kindly fix.

Thanks a TON.

Regards...............SKG
SOMG_TX

2CA04, C-Block, 2nd Floor,
DAKC.

Direct: +91 22 303 82104
RIM: +91 9322598171



"Meera Bharti" <bharat...@hiranandani.net>

02/25/2009 10:40 AM

       
        To:        <Sanjay....@relianceada.com>
        cc:        <Chandra...@relianceada.com>, <manoj....@gmail.com>, "Cm Mate" <mat...@hiranandani.net>, <Mayflo...@googlegroups.com>, "MayflowerMgc" <mayflo...@gmail.com>, <m.sa...@tcs.com>, "Anil Nambiar" <nambia...@hiranandani.net>, "P Premchandran" <p.premc...@hiranandani.net>, <rpriy...@yahoo.co.in>, <sushi...@ril.com>, <S.Srin...@ticb.com>, <trid...@hotmail.com>, <xavier...@yahoo.com>
        Subject:        RE: Mayflower/ Pls. resolve all pending Issues before final hand-over.


 Importance: Normal Sender's OU: Reliance




Dear Mr. Gupta
 
I assure you that we will definitely arrange the meeting with the planning and project and myself in the next week. ( is 7th March, Saturday at Mate’s office OK with you?)
 
Thanks for your positive approach. But we will keep the final cut off date as 28/02/2009. The SAP period closes on 1st March,09. Please co-operate to resolve the issue.
 
Appreciate your help.

 
Regards
Meera Bharati
B.Com. A.C.A.
DGM-Finance
Hiranandani Group

 
 
From: Sanjay....@relianceada.com [mailto:Sanjay....@relianceada.com]
Sent:
Tuesday, February 24, 2009 7:11 PM
To:
Meera Bharti
Cc:
Chandra...@relianceada.com; manoj....@gmail.com; Cm Mate; Mayflo...@googlegroups.com; MayflowerMgc; m.sa...@tcs.com; Anil Nambiar; P Premchandran; rpriy...@yahoo.co.in; sushi...@ril.com; S.Srin...@ticb.com; trid...@hotmail.com; xavier...@yahoo.com
Subject:
RE: Mayflower/ Pls. resolve all pending Issues before final hand-over.

 

1.        Thank you for all your kind supports and commitment.


2.        We agree to you and absolutely don’t have any apprehension in your requirement of closing the Mayflower maintenance A/c in SAP.


3.        We would like to request you to kindly review our 18 punch points (
Reference our letter Ref: LH-0608/01 dtd. 17th June 2008). Some of these may require some additional inventory/ expenses and not just related to Man-hours. Request you and your project colleagues to ensure that there is no hurdle in its completion.

4.        If required, a joint discussion/ review of above pt. 3 with your project team @ site can be planned to avoid any such remote issue before SAP closure.  


Thanks& Regards...............SKG

2CA04, C-Block, 2nd Floor,
DAKC.

Direct: +91 22 303 82104
RIM: +91 9322598171

"Meera Bharti" <bharat...@hiranandani.net>

02/24/2009 05:01 PM

       
       To:        <Sanjay....@relianceada.com>
       cc:        "Cm Mate" <mat...@hiranandani.net>, <Mayflo...@googlegroups.com>, "MayflowerMgc" <mayflo...@gmail.com>, "Anil Nambiar" <nambia...@hiranandani.net>, "P Premchandran" <p.premc...@hiranandani.net>, <Chandra...@relianceada.com>, <m.sa...@tcs.com>, <manoj....@gmail.com>, <S.Srin...@ticb.com>, <trid...@hotmail.com>, <xavier...@yahoo.com>, <rpriy...@yahoo.co.in>, <sushi...@ril.com>
       Subject:        RE: Mayflower/ Pls. resolve all pending Issues before final hand-over.


Importance: Normal Sender's OU: Reliance





Dear Mr. Gupta

As already mentioned by you, we always give the technical support to all our buildings, after the handover also. Please understand that, we have SAP system and no society can be maintained more than 24 months. Thus the society orders will get blocked automatically. Thus physical support in case of the manpower will be always there for any construction related issues.

As asked by you, the conveyance will happen when all the plots in that area (Medows) are developed.

TMC approved plans you will get in a period of 4 to 5 working days.

Regarding the Entry and Exit issues , I told you that we had a personal visit and expecting a answer in 8/10 days time from the planning department.

These all are the external points having no connection with the accounts and maint. Issues. These are the principal issues. Thus taking over is always means the accounts and financial take over. Our support is always there. And as you mentioned that mostly 80 % of the services are being taken over thus the remaining can be taken over from March-09.

Regards


Meera Bharati
B.Com. A.C.A.
DGM-Finance
Hiranandani Group

Sanjay....@relianceada.com

unread,
Feb 24, 2009, 8:41:08 AM2/24/09
to Meera Bharti, Chandra...@relianceada.com, manoj....@gmail.com, Cm Mate, Mayflo...@googlegroups.com, MayflowerMgc, m.sa...@tcs.com, Anil Nambiar, P Premchandran, rpriy...@yahoo.co.in, sushi...@ril.com, S.Srin...@ticb.com, trid...@hotmail.com, xavier...@yahoo.com

Meera Bharti

unread,
Feb 25, 2009, 12:10:35 AM2/25/09
to Sanjay....@relianceada.com, Chandra...@relianceada.com, manoj....@gmail.com, Cm Mate, Mayflo...@googlegroups.com, MayflowerMgc, m.sa...@tcs.com, Anil Nambiar, P Premchandran, rpriy...@yahoo.co.in, sushi...@ril.com, S.Srin...@ticb.com, trid...@hotmail.com, xavier...@yahoo.com

Dear Mr. Gupta

 

I assure you that we will definitely arrange the meeting with the planning and project and myself in the next week. ( is 7th March, Saturday at Mate’s office OK with you?)

 

Thanks for your positive approach. But we will keep the final cut off date as 28/02/2009. The SAP period closes on 1st March,09. Please co-operate to resolve the issue.

 

Appreciate your help.

 

Regards

Meera Bharati
B.Com. A.C.A.
DGM-Finance
Hiranandani Group

 

 

Sent: Tuesday, February 24, 2009 7:11 PM
To: Meera Bharti

Meera Bharti

unread,
Feb 24, 2009, 6:31:37 AM2/24/09
to Sanjay....@relianceada.com, Cm Mate, Mayflo...@googlegroups.com, MayflowerMgc, Anil Nambiar, P Premchandran, Chandra...@relianceada.com, m.sa...@tcs.com, manoj....@gmail.com, S.Srin...@ticb.com, trid...@hotmail.com, xavier...@yahoo.com, rpriy...@yahoo.co.in, sushi...@ril.com

Dear Mr. Gupta

 

As already mentioned by you, we always give the technical support to all our buildings, after the handover also. Please understand that, we have SAP system and no society can be maintained more than 24 months. Thus the society orders will get blocked automatically. Thus physical support in case of the manpower will be always there for any construction related issues.

 

As asked by you, the conveyance will happen when all the plots in that area (Medows) are developed.

 

TMC approved plans you will get in a period of 4 to 5 working days.

 

Regarding the Entry and Exit issues , I told you that we had a personal visit and expecting a answer in 8/10 days time from the planning department.

 

These all are the external points having no connection with the accounts and maint. Issues. These are the principal issues. Thus taking over is always means the accounts and financial take over. Our support is always there. And as you mentioned that mostly 80 % of the services are being taken over thus the remaining can be taken over from March-09.

 

Regards

 

Meera Bharati
B.Com. A.C.A.
DGM-Finance
Hiranandani Group

 

Sent: Tuesday, February 24, 2009 4:33 PM
To: Meera Bharti
Cc: Cm Mate; Mayflo...@googlegroups.com; MayflowerMgc; Anil Nambiar; P Premchandran; Chandra...@relianceada.com; m.sa...@tcs.com; manoj....@gmail.com; S.Srin...@ticb.com; trid...@hotmail.com; xavier...@yahoo.com; rpriy...@yahoo.co.in; sushi...@ril.com