PRE HEAT PROCEDURE OF E 7016 -1 ELECTRODE

711 views
Skip to first unread message

jiji lal

unread,
Apr 13, 2013, 1:06:57 AM4/13/13
to material...@googlegroups.com
SIR,

I'm engaged with welding of API 5LX 80  grade pipeline for regassified LNG transmission . We do  Tie-in method using SMAW+FCAW.
For root pass welding we use E7016-1 electrode after pre heating 250 degree for 2 hr in mother oven and maintain 100 degree in holding oven . during RT interpretation severe hollow bead and porosity observed in root .hence PMC sent almost all joints for repair.now it becomes a serious issue and I think ,the pre heat method was not proper. kindly advice me in this issue.

Mr.Jijilal k .m
qa/qc dept. tecpro ltd.
kochi.

Srini Vasan

unread,
Apr 13, 2013, 11:05:30 PM4/13/13
to material...@googlegroups.com
Dear,
        Do you have Approved consumable Control procedure from your client? then, if you follow the Preheat method as per procedure then no need to worry..check the cause problem,,you will find any way.


--
To post to this group, send email to material...@googlegroups.com
To unsubscribe from this group, send email to materials-weld...@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
 
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-weld...@googlegroups.com.
For more options, visit https://groups.google.com/groups/opt_out.
 
 



--
With Best & Regards

cid:image002.jpg@01C97F91.23410920
N.Srinivas,
Welding Inspector,
Al Suwaiket Industrial Support Services,
0561198050,0537812787
Al-Khobar.
image001.jpg

c sridhar

unread,
Apr 13, 2013, 1:45:09 PM4/13/13
to material...@googlegroups.com
Mr. Lijilal,

a. Please check up the date of manufacturing of the electrode. Generally up to 12 months is OK, but not for
    xay quality welds. 6 months  from manf. date should be better.

b. Dry the electrodes at 300 deg. C  for min. 2 hrs and not the total duration.

c. If required dry them at 350 deg. C for 1 hour and see the results. may be it should be OK.

d. Change the brand if it is also  not working  out.

Sridhar.


From: jiji lal <jiji...@gmail.com>
To: material...@googlegroups.com
Sent: Saturday, 13 April 2013 10:36 AM
Subject: [MW:17372] PRE HEAT PROCEDURE OF E 7016 -1 ELECTRODE

Nandesh Kumar

unread,
Apr 13, 2013, 1:38:41 PM4/13/13
to material...@googlegroups.com

Check/try the following:

As far as consumables are concerned:
  1. Bake (not preheat!) the electrodes, as per the manufacturer's recommended duration.
  2. Ensure the numbers 250, 100 what you have mentioned are not in ° F !! it should be ° C.
  3. If Vac-Pac electrodes are used, do not bake.
  4. Check baking oven, holding oven and quivers are properly calibrated.
  5. Limit the number of rebaking cycles to manufacturer recommendation.
  6. Check the shelf-life of electrodes with the manufacturer.
Others:
  1.  If pre heat is needed, before welding, check the pre heat of base metal is done properly, using approved procedures.
  2. Ensure the cleanliness of the area to be welded.(face, bevel, inside, outside for 1" minimum)
  3. Ensure sufficient wind protection is provided during welding.
  4. Ensure qualified welders are being used.
  5. Ensure approved WPS is being used.
Above mentioned are 'generalized' precautions only. If you provide some more data, it can be analyzed further.

ವಂದನೆಗಳೊಂದಿಗೆ / Best regards,

Nandesh Kumar Arasappa

P.S. : Please don't print this e-mail unless you really need to.


--- On Sat, 13/4/13, jiji lal <jiji...@gmail.com> wrote:

From: jiji lal <jiji...@gmail.com>
Subject: [MW:17372] PRE HEAT PROCEDURE OF E 7016 -1 ELECTRODE
--

HAREESH K V

unread,
Apr 15, 2013, 12:54:12 AM4/15/13
to materials-welding
Just to clear one doubt, may be wrong. 

Can it be because of pipe material?

May you try the consumable to weld a different/compatible base material, like SA106GrB, just on a sample piece with same welding procedure and do the radiography.

Just to confirm the issue is because of consumable itself.

Also may be the problem is because pf residual elements in the base material. Please check the MTC of pipe material.

Regards,

Hareesh K V

vdthuan

unread,
Apr 14, 2013, 9:14:05 PM4/14/13
to material...@googlegroups.com

Hi,

You are fully complied with procedure already as you mentioned below, but I think you should check the welding condition like wind prevent,..or preheat before welding…

Wish you success

 

Best Regards,

Vu Duc Thuan

Phone: +84(0) 983 017 936

 

From: material...@googlegroups.com [mailto:material...@googlegroups.com] On Behalf Of jiji lal
Sent: Saturday, April 13, 2013 12:07 PM
To: material...@googlegroups.com
Subject: [MW:17372] PRE HEAT PROCEDURE OF E 7016 -1 ELECTRODE

 

SIR,

 

Mr.Jijilal k .m

qa/qc dept. tecpro ltd.

kochi.

--

Surendran

unread,
Apr 15, 2013, 7:57:05 AM4/15/13
to material...@googlegroups.com, <materials-welding@googlegroups.com>
Hi

I think you check the welder also wether they got do proper interpass cleaning and did the welder using a fan? And is the fan is near to the welding area. 

james gerald

unread,
Apr 15, 2013, 7:19:39 AM4/15/13
to material...@googlegroups.com
Check whether you are complying with welding consumable manufacturer recommendation on Baking of electrodes.
 
If the answer is Yes, then check for
 
1. Whether wind protection is there by providing proper shields.
2. Whether welder is good
3. Whether base material contains mositure etc.. then m you may preheat the joint
4. whether Grease or carbonaceous material present in the base material, then do proper cleaning using some solvent
 
 
Thanks & Regards

J.Gerald Jayakumar
00968-99438165
From: vdthuan <dthu...@gmail.com>
To: material...@googlegroups.com
Sent: Monday, April 15, 2013 5:14 AM
Subject: [MW:17391] RE: 17372] PRE HEAT PROCEDURE OF E 7016 -1 ELECTRODE
Reply all
Reply to author
Forward
0 new messages