Hydro test-max holding period

1,259 views
Skip to first unread message

Aarpee

unread,
Oct 24, 2008, 2:29:40 AM10/24/08
to Materials & Welding
As per B31.3 Hydro test is carried out at 1.5X Design Pressure.Holding
time for Piping spools is normally 30 minutes but at times 4-6 hours
for Gas applications.Can this be held for 24 hours?What is the
potential risk?It is normally indicated that after Hydro inspection
for 10-30 minutes at 1.5X Design Pressure,if you intend doing further
inspection then same can be done at a pressure not more than the
design pressure.Opinion of the group is being sought thro this mail
Regards
Aarpee

Kannan....@linde-le.com

unread,
Oct 24, 2008, 4:02:08 AM10/24/08
to material...@googlegroups.com, piping...@yahoogroups.com

The holding period depends on the time needed for inspecting the system thoroughly. Minimum is 10 minutes. Especially the gas tests calls for 100% weld and mechanical joints being examined.
Also we have to ensure the limits of test pressure defined by individual components also to be taken care not to damage the components for eg. the soft seating or lining or to replace them with pipe spools.

To my info the repeated call for Hydrostatic test on the same system, the pressure need not be changed from the code to its design pressure as most of the case if any major leaks are identified, the test is performed again at the same pressure and not to reduced pressure. It is independent of the holding time. Holding time risk are purely defined by inspecting time and the in-line components and not of the piping components. It is a usual practice to remove all in-line components which has reduced testing pressure conditions.

The maximum test pressure is the pressure at which the pipe reaches its yield stress. In most of the cases the problems can be tracked back to the original thickness calc of the piping system where in somecases you may find the thickness not sufficient to take the test pressures but will suit the design pressure. When you design the piping class for rating condition you may have some margins to accommodate the test pressure but not always especially in the larger size range above 24". This makes the site testing team to reduce the test pressure adjusting to actual pipes purchased and being used and of the elevation impact of the system. Also piping connected with vessels pose a diff. situation and defining the test pressures requires a different judgement as the approach differs from company to company.

Most important thing is to question the need of hydrotest for a system to process dept. who defines the requirement.

Regards,
Kannan.



Aarpee <rampras...@gmail.com>
Sent by: material...@googlegroups.com

24/10/2008 08:29


To
"Materials & Welding" <material...@googlegroups.com>
cc
Subject
[MW:1236] Hydro test-max holding period


CKPurohit

unread,
Nov 3, 2008, 2:50:37 AM11/3/08
to material...@googlegroups.com

Dear All,

 

Can somebody guide me what are the requirement for PQR qualification for plug weld.

 

I need to weld the plugs of SS liner on the Cr Mo Body (outer shell).

 

Regards.

CK


***DISCLAIMER NOTICE ***
"This e-mail and any files transmitted with it is confidential and is intended only for the use of the recepient(s) named above.
If you are not the intended recipient, any review, retransmission, dissemination, distribution, printing, copying or use the information contained in this message or any part thereof in other manner is strictly prohibited.
If you receive this e-mail in error, please notify the sender immediately by return e-mail and delete the e-mail and any of its attachments.
Any personal views or opinions expressed by the sender shall be understood as neither given nor endorsed by KNM or any of the companies within the Group."

carlos oliveros

unread,
Nov 4, 2008, 7:10:50 AM11/4/08
to material...@googlegroups.com

Hi, CK, What is the construction standard. ASME IX , Section II is the guide.

What Number P SS is P8 and Cr Mo pending the percent Cr Mo(P4, P5).

Give information more

carlos oliveros

On Mon 03/11/08 03:50 , "CKPurohit" c...@knm-group.com sent:

CKPurohit

unread,
Nov 5, 2008, 10:00:10 PM11/5/08
to material...@googlegroups.com

Dear Carlos,

 

Construction code is Sec VIII (so we need to follow Sec IX) Vessels are code stamped.

 

P No for Cr Mo is P4 and for SS is P8 Gr 2

 

But the info I need only for plug welds which clause to be referred in Sec IX to find out PQR and performance qualification requirement.

 

Regards.

CK


</HTML

mathu.subramanian

unread,
Nov 6, 2008, 1:25:24 AM11/6/08
to material...@googlegroups.com

Please refer QW 382.2.

 


Ali Asghari

unread,
Nov 11, 2008, 3:03:01 AM11/11/08
to material...@googlegroups.com
hi
because types of weld stated in IX are groove & partially groove & fillet & spot,therefore i soppose you qualify your plug weld with groove weld(if your components retain pressure)otherwise by fillet .


From: CKPurohit <c...@knm-group.com>
To: material...@googlegroups.com
Sent: Monday, November 3, 2008 11:20:37 AM
Subject: [MW:1266] Sec IX requirement for plug welds
Reply all
Reply to author
Forward
0 new messages