--
To post to this group, send email to material...@googlegroups.com
To unsubscribe from this group, send email to materials-weld...@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
Could you clarify what is the application code? Section I, section VIII-1?
Yes, you can support this PQR, since you have valid impact test report
Vasanth
Then you will find your answer in USC-67.
If you do not have the code or you have interpretation problems let me know.
--
To post to this group, send email to material...@googlegroups.com
To unsubscribe from this group, send email to materials-weld...@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
As you have stated, ER 70 S3 are normally manufactured to meet -20 Deg criteria as per standard requirements ASME Sec II C. However if your project requirement calls for -46 Deg C, the filler metal also need to be procured with the filler metal certified to this as a special requirement or if your client accepts all filler wire batches can be tested at external lab. Note that testing at external lab might lose the filler metal manufacturers liability in case of problems. This is in addition to the fact that the PQR has passed the -46 Deg C requirement.
With Regards,
V.Vaidyanathan
Welding Inspection Engineer │ Worley Parsons│Kuwait
(
+965 238 61657 │ Fax. +965 2398 1695
www.worleyparsons.com
From: material...@googlegroups.com [mailto:material...@googlegroups.com] On Behalf Of kannayeram gnanapandithan
Sent: Saturday, April 03, 2010
6:29 PM
To: material...@googlegroups.com
As you have stated, ER 70 S3 are normally manufactured to meet -20 Deg criteria as per standard requirements ASME Sec II C. However if your project requirement calls for -46 Deg C, the filler metal also need to be procured with the filler metal certified to this as a special requirement or if your client accepts all filler wire batches can be tested at external lab. Note that testing at external lab might lose the filler metal manufacturers liability in case of problems. This is in addition to the fact that the PQR has passed the -46 Deg C requirement.
With
Regards,
V.Vaidyanathan
Welding Inspection Engineer │ Worley
Parsons│Kuwait
(
+965 238 61657 │ Fax. +965 2398 1695
www.worleyparsons.com
Then you will find your answer in USC-67.
If you do not have the code or
you have interpretation problems let me know.
From: Muhammed Ibrahim [ibra...@gmail.com]
Sent:
02/04/2010 16:34 ZE4
To:
material...@googlegroups.com
Subject: Re: [MW:4670]
ER70S-3 for low temperature application
Could you clarify what is the application code? Section I, section VIII-1?
From: material...@googlegroups.com [mailto:material...@googlegroups.com] On Behalf Of Raghuram Bathula
Sent: Thursday, April 01, 2010 12:42 PM
To: material...@googlegroups.com
Subject: Re: [MW:4665] ER70S-3 for low temperature application
Yes, you can, however you may ensure each batch is tested for impact at this temperature though it is not a requirement
Let us take the thinks one by one
1. Your base metal is exempted from impact test
2. Your MDMT is 46 deg
3. Your filler material ER60S-3 is per spec at -20 deg
4. Your WPS was successfully qualified at -46
Conclusion: you can use this WPS for that combination of base metal and filler metal and MDMT warmer than -46 Deg C with no additional filler metal test.
I suppose you have checked compliance of your fabrication process with UG 84 regarding production impact test.
Regards
Dear Ibrahim,
In order to assure, each batch shall be tested for impact toughness test at MDMT in addition to test conducted during PQR qualification. In general filler metal manufacturer will satisfy the requirements of ASME Sec. II Part ‘C’. Any additional requirements shall be communicated to the manufacturer in PO itself in order to meet the testing requirements.
Some of the reputed manufacturers such as Lincoln, Bohler could able to meet the above requirements. Please enquire with them.
Regards,
L. Prabhu kumar,
Sr. Principal Engineer,
Equipments & Materials Dept.,
Saipem India Projects Limited,
Nungambakkam High Road, Chennai - 600 034, India.
Tel:+91 44 43906588, Ext.: 588, Fax:+91 44 66840345,
Mobile Ph. No.: +91 9003010978.
------------------------------------------------------------------------------------------------------------------------------------------------------------------- DISCLAIMER: The information contained in this communication is intended solely for the use of the individual or entity to whom it is addressed and others authorized to receive it. It may contain confidential or legally privileged information. If you are not the intended recipient, you are hereby notified that any disclosure, copying, distribution or taking any action in reliance on the contents of this information is strictly prohibited and may be unlawful. If you have received this communication in error, please notify us immediately by responding to this email and then delete it from your system. Saipem India Projects Limited (SIPL) is neither liable for the proper and complete transmission of the information contained in this communication nor for any delay in its receipt. ------------------------------------------------------------------------------------------------------------------------------------------------------------------- |