Closure/ Tie in joints - NDEs as per B31.3

1,764 views
Skip to first unread message

VJ V

unread,
Mar 5, 2009, 4:56:45 PM3/5/09
to Materials & Welding

Hi All,

There are a couple of Tie-in/Closure joints to be welded in the
project, I am involved right now. No possibility of Leak test/
Hydrotest for that joint..

Project spec is ASME B31.3(100% RT),and
I would like to know is there any requirement of UT and cut bevel MT/
UT,additional to RT specified by the Code for Closure/ Tie in joints.

I couldn't see that requirement(cut bevel MT,UT) in B 31.3......Am I
right ?

I have done earlier UT,cut bevel MT additional to RT in other
projects,but that was as per project spec.

Thanks

syed farhan rezvi

unread,
Mar 7, 2009, 2:25:22 AM3/7/09
to material...@googlegroups.com
hi to all,

As i believe after reading your mail it's a TIE-IN between
old and new line,
if it so, please do UT for thickness checking in the old & MT on same
line in bevel and HAZ( you can prefer PT if the thickness of line is
less than 19 mm).


Syed Farhan
Piping Engineer
Hyundai Heavy Industries

VJ V

unread,
Mar 7, 2009, 4:46:50 AM3/7/09
to Materials & Welding
Hi Syed,

Thanks for reply..
Yes, I know thats the normal practice, UT and MT in Tie-ins..But, Is
there any thing with regards to this mentioned in the code B 31.3 or
even B31.4 / B 31.8..

Regards


On Mar 7, 10:25 am, syed farhan rezvi <samre...@gmail.com> wrote:
> hi to all,
>
>            As i believe after reading your mail it's a TIE-IN between
> old and new line,
> if it so, please do UT for thickness checking in the old & MT on same
> line in bevel and HAZ( you can prefer PT if the thickness of line is
> less than 19 mm).
>
> Syed Farhan
> Piping Engineer
> Hyundai Heavy Industries
>
> On 06/03/2009, VJ V <veeve...@gmail.com> wrote:
>
>
>
>
>
> > Hi All,
>
> > There are a couple of Tie-in/Closure joints to be welded in the
> > project, I am involved right now. No possibility of Leak test/
> > Hydrotest for that joint..
>
> > Project spec is ASME B31.3(100% RT),and
> > I would like to know is there any requirement of UT and cut bevel MT/
> > UT,additional to RT specified by the Code for Closure/ Tie in joints.
>
> > I couldn't see that requirement(cut bevel MT,UT) in B 31.3......Am I
> > right ?
>
> > I have done earlier UT,cut bevel MT additional to RT in other
> > projects,but that was as per project spec.
>
> > Thanks- Hide quoted text -
>
> - Show quoted text -

HAREESH K V

unread,
Mar 7, 2009, 7:46:53 PM3/7/09
to material...@googlegroups.com
In ASME B31.3 please refer 345.2.3. In there itz mentioned about closure welds

Regards

Hareesh K V

--
----------------------
Hareesh K V
+91-9447625021

Rituraj Bose

unread,
Mar 6, 2009, 8:28:23 AM3/6/09
to Materials & Welding
Hi VJV,
As per Para 345.2.3 (c) of ASME B31.3 (2006 edn.), you can either do
100% RT or 100% UT. If Project Specification asks for, you may have to
do PT or MT after root pass as per Para 344.7, if nothing mentioned in
Project Specifications, you can go ahead only for 100% RT and you are
right that no additional requirement is there in B31.3.
Regards,
R. Bose

VJ V

unread,
Mar 10, 2009, 4:47:35 AM3/10/09
to Materials & Welding

Thanks Ritu raj for you prompt reply.....
Regards
VJv