Clause 328.2.3 Performance Qualification by Others.- specifies what require to be done for transfer of qualification for welders to the present employer
I hope clause 328.2.2 and 328.2.3 would help to clarify your query.
Thanks.
--
To post to this group, send email to material...@googlegroups.com
To unsubscribe from this group, send email to materials-weld...@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
--
To post to this group, send email to material...@googlegroups.com
To unsubscribe from this group, send email to materials-weld...@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
Hi,
The subcontractor no need to prepare WPS,because the EPC contractor is full resposible for all welding activities and he just use the subcontractor to finish the job. So the Subcontractor can use WPS/PQR of the EPC contractor.
Thanks & Regards,
(Karthik)
Karthikeyan.S
QA/QC Manager
Getabec Energy Co.,Ltd.
379,Moo6,Soi8,Nikhomphatana,
Rayong-21180,
Thailand.
Phone: 0066 38 897035-8 (Off)
Fax: 0066 38 897034
Hand Phone: 0066 892512282 --- On Wed, 9/7/11, raj roy <katkar....@gmail.com> wrote: |
|