Hi,
Is it a cladding lining? or internal parts attached to inside of the equipment?
If it is like a cladding internal,pls.refer section UCL of Section VIII,div.1.,it clearly specified that the heat treatment shall be done together with the SS or any cladding.
if it is a internal parts to be welded inside,you can weld a pad plate with the same vessel material and go for the PWHT. After PWHT finished you can weld the ss316 parts with the pad plate as welded.
Finally, If your customer accepts to proceed the PWHT with SS316 internal,you can go ahead.Normally customer/Project specification over rules all as they are the end user.I think your QC worried about the SS316 chemical properties after PWHT(corrosion resistant). this can be avoid by doing pickling and passivation after PWHT.
Thanks & Regards,
(Karthik)
Karthikeyan.S
QA/QC Manager
Getabec Energy Co.,Ltd.
379,Moo6,Soi8,Nikhomphatana,
Rayong-21180,
Thailand.
Phone: 0066 38 897035-8 (Off)
Fax: 0066 38 897034
Hand Phone: 0066 892512282 --- On Wed, 8/3/11, Vijay <k.vij...@gmail.com> wrote: |
|
- Remove internals,
- weld an internal ring (same material as the shell) to the vessel (later you will weld internals to this ring),
- carry out PWHT on vessel without internals and then
- weld the internals to that internal ring...
Hi,
I think you misunderstood.
1. Weld pad plate with same material(same P.No.) to the shell/Pipe ( if your internals cover full of the inside of the sheel it may be of ring type or weld pad plate where internal are to be there) (WPS P1 to P1)
2. Proceed PWHT without SS316 internals.
3.After PWHT, weld SS316 internals to the Pad palte or ring as you welded with the shell/pipe before PWHT (WPS for P1 to P8)
Conduct NDE as applicable.
No need to do PWHT again,because you have not welded any direct to the shell after PWHT. |
Thanks & Regards,
(Karthik)
Karthikeyan.S
QA/QC Manager
Getabec Energy Co.,Ltd.
379,Moo6,Soi8,Nikhomphatana,
Rayong-21180,
Thailand.
Phone: 0066 38 897035-8 (Off)
Fax: 0066 38 897034
Hand Phone: 0066 892512282 --- On Wed, 8/3/11, Vijay <k.vij...@gmail.com> wrote: |
Mr.Vijay,
As Mr.Arunachalam said,If you have a suitable WPS with PWHT then you can proceed to PWHT with SS internal and after that you can do pickling on SS316 parts.You can convince your QC person that your customer also accepts to do PWHT with SS internals. Finally we shall follow customer's requirement/specification unless otherwise if there is any big conflict to the CODE requirements.In your case its not.you can go ahead. |
Thanks & Regards,
(Karthik)
Karthikeyan.S
QA/QC Manager
Getabec Energy Co.,Ltd.
379,Moo6,Soi8,Nikhomphatana,
Rayong-21180,
Thailand.
Phone: 0066 38 897035-8 (Off)
Fax: 0066 38 897034
Hand Phone: 0066 892512282 |
--- On Mon, 8/8/11, Arunachalam A <arun...@gmail.com> wrote: |
|