Below is the recommendation for the fabrication of P91 material you can check reference for make PQR & WSP
Cutting
Cutting of P91 material shall be done only with Band Saw. Edge Preparations (EP) shall be done only by machining, however gas cutting can also be done but at least 3 mm of material required to be remove to avoid high hardness due to gas cutting process. All Edge Preparations (EPs) shall be subjected to Liquid Penetrant Test (LPT) or MT. Weld Build-up on EP shall be prohibited.
Weld Fit-up
Welding of P91 Material:
Preheating→Preheat Maintenance→Welding→Post Heating→Cooling below 96°C→PWHT
Preheat:
A minimum preheat of 204°C shall be maintained throughout the welding process. Heating shall be by electric resistance method/induction heaters. A minimum preheat of 204°C shall be used for tack welding. For tack welds incorporated into the final weld, preheat shall be maintained at 204°C through the completion of welding. Preheat and Interpass temperatures shall be monitored and recorded manually by Thermo pens or Laser Guns. A manual record for Interpass temperatures shall be maintained for each pass. The minimum preheat temperature may be reduced to 150°C when the weld thickness is less than ½ inch (13mm) and welding is performed by the GTAW process. Preheat can only be reduced to 150°C when allowed by the governing Code.
Recommended preheat temperature for Grade 91 material as per various codes and standards:
205°C (Non-Mandatory appendix “R”, ASME Section VIII Div.1)
200°C (Table 131.4.1-1, ASME B31.1 & Table 330.1.1 of ASME B31.3)
150°C for thickness ≤13 mm & 205°C for thickness > 13 mm (Table PW-38-1, ASME Section 1)
Preparation after Welding
Hydrogen Bake-out:
After completion of welding it is to be ensured that joint put in Hydrogen Back-out. Hydrogen Baking is to be performed and maintained with Resistance heating method. The weld shall receive a post heating between 300°C to 350°C.The weld shall be post heated for a minimum of 2 hours and a maximum of 3 hours and then wrapped with insulation and slow cooled down to at least 96°C, at which time the weld may be unwrapped. For welds deposited by GTAW process, the post heat temperature may be reduced to 260°C minimum. After satisfactory completion of Hydrogen baked out, complete weld joint and HAZ shall be visually examined for any surface Indication, visually accepted welded joint shall be sent for PWHT. There shall not be delay of more than 5 days for PWHT, after completion of Hydrogen baking of the joint.
Cooling after Post Heating:
To achieve post weld tempering of the martensitic structure, it is important that the weld joint cools below martensitic temperature before heat treatment. The martensitic finish (Mf) temperature of P91 is approximately 96°C. Therefore, it is recommended to cool below 90°C to allow complete transformation of the weld metal and heat affected zone.
Post Weld Heat Treatment (PWHT) of Grade P91:
PWHT
is one of the most important factors in producing satisfactory weld of P91
material. Regardless of the thickness or diameter preheating and PWHT are
mandatory to reduce hardness and to restore ductility in the weld and HAZ.
Selection of P91 steel PWHT temperature range is very tricky as we have to
follow construction code and also depends & affected by percentage of Mn+Ni
as it lowers the lower critical transformation temperature. Selection of proper
soaking temperature is very
important in case of P91 material. If the PWHT temperature is too low, the
welds joints lead to insufficient toughness and high hardness due to the
unsatisfactory tempering effect and if the PWHT temperature is too high, the
tensile strength at ambient and elevated temperatures becomes inadequate due to
over tempering effect.
PWHT temperature as per various codes and standards:
For welds made with matching Grade 91 filler metal (e.g., AWS A.5.5 E90xx-B91, ISO EN CrMo91), the maximum holding temperature shall be determined as follows:
Recommended PWHT temperature for P91 Material are 740 to 760°C
Preventive measures during any interruption of heating/welding at any stage:
Weld Interruption-Weld interruptions are defined as either an unintentional loss of preheat or reductions below the minimum preheat temperature after welding has begun.
Welding of P91 requires heat application throughout the process. As the cycle time is long, there are chances of Heating/Welding interruption due to non-availability of-Power
Steps to be taken in case power is not available for heating during P91 Welding:
Steps to be taken for some of the realistic eventualities occur in shop floor during P91 welding:
Filler Metal Selection for P91 material
Consumables Listed in ASME for Welding P91:
When using SAW, a basic flux is preferred since other flux types will burn out carbon and permit elevated oxygen and nitrogen levels reducing the strength and toughness of the weld metal.
Heat Treatment of P91 Material
Modified 9Cr-lMo requires a normalize and temper heat treatment to fully develop its strength and toughness properties. Standard practice is to normalize between 1040 to 1090 °C to avoid objectionable grain growth, and tempering at 760 to 780 °C which allows carbides to precipitate homogeneously within the tempered fully martensitic structure.
The lower critical temperature between 830 °C to 850 °C;
The upper critical Ac3 exists between 900 to 940°C
Microstructure of Grade P91
P91 steel has been widely used in power generation industry. Generally, P91 creep resisting steel is produced by normalizing and tempering.The microstructure after tempering is tempered martensite with precipitates of carbides, M23C6, and vanadium/niobium rich carbo‐nitride of the type MX (M = V or Nb and X = C or N).
--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-weld...@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CANOYChzbp9mT2D4-ihKe6XWBcQMOxjHeU3%3DiRjLRYMQiKzBOew%40mail.gmail.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAEVAJwYOgwjASZb8O2k%3D%3DvKZkhj9GCSQEDTgRCR0REbkdPK3fw%40mail.gmail.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CANOYChzjbu2OYgNM6a4O7_2Owo0D9E58%3DiWbTs15AF%3DN%3D60MHg%40mail.gmail.com.
On 21-Nov-2022, at 12:26 PM, Kannayeram Gnanapandithan <kgpan...@gmail.com> wrote:
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAJzm4eOQOQ1%2B6mT8Vi0Skz6WVa%3D93uipkq__yjkuY-GAV0Ordw%40mail.gmail.com.