Dear Experts,
In a project, Is it always necessary to do PMI on all Stainless welds or whether it is a clent requirement only. Code followed is ASME B 31.1
S.Binoy
Dear Mr.Binoy,
Not necessary , it depends on project spec. and how confident in working system. For me , we will perform PMI internally anyway to double check correct material grade and correct welding rod.
Be aware that some PMI spec. require to check Carbon on high or low carbon stainless such as 316L or 347H , etc. Normal PMI cannot perform this check and you have to use portable spectrometer which will be much more costly. You have to review PMI spec. and material you are welding carefully.
Regards,
C.Nopadon
From: material...@googlegroups.com [mailto:material...@googlegroups.com] On Behalf Of Binoy Soman
Sent: Wednesday, February 27, 2013 1:10 AM
To: material...@googlegroups.com
Subject: [MW:16879] PMI on Stainless Steel Welds
Dear Experts,
In a project, Is it always necessary to do PMI on all Stainless welds or whether it is a clent requirement only. Code followed is ASME B 31.1
S.Binoy
--
Client specified but Generally we do 10%-20% Pmi for all ss welds.
Regards
L.patra
--
Hi
PMI test for SS and Alloy steel is client requirement and same is mentioned in QAP / project specs..
It is not code requirement.
Regards
Prem Nautiyal
9769316004
|
|
|
| Gents, It is generally understood that PMI result reliability is as low as +/- 15%. It is mostly what can be called as go/no go type of test. Can any one confirm if ASME accepts PMI (by XRF) / Spectrometry and under what conditions. Rgds, |
Pradip Goswami,P.Eng.IWE
Welding & Metallurgical Specialist
Ontario, Canada.
136.1.3
Rights of Inspectors. Inspectors shall have access to any place where work concerned with the piping is being performed. This includes manufacture, fabrication, heat treatment, assembly, erection, examination, and testing of the piping. They shall have the right to audit any examination, to inspect the piping using any appropriate examination method required by the engineering design or this Code, and to review all certifications and records necessary to satisfy the owner’s responsibility as stated in para. 136.1.1.Verification of Compliance.
Prior to initialoperation, a piping installation shall be inspected toensure that the piping has been constructed in accordancewith the design, material, fabrication, assembly, examination, and testing requirements of this Code
API RECOMMENDED PRACTICE 578, Material Verification Program for New and Existing Alloy Piping Systems
The purpose of this recommended practice is to provide the guidelines for a material and quality assurance system to verify that the nominal composition of alloy components within the pressure envelope of a piping system is consistent with the selected or specified construction materials to minimize the potential for catastrophic release of toxic or hazardous liquidsor vapors.
This recommended practice provides the guidelines formaterial control and material verification programs on ferrous and nonferrous alloys during the construction, installation,maintenance, and inspection of new and existing process piping systems covered by the ASME B31.3 and API 570 piping codes. This practice applies to metallic alloy materials purchased for use either directly by the owner/user or indirectly through vendors, fabricators, or contractors and includes the supply, fabrication, and erection of these materials. Carbon steel components specified in new or existing piping systems are not specifically covered under the scope of this document.