production test coupon requiorement as per ASME SEC VIII DIV 1

10,569 views
Skip to first unread message

asad azmi

unread,
Nov 26, 2010, 6:00:01 AM11/26/10
to material...@googlegroups.com
Dear all,
 
Greetings.
 
Please inform me PTC(Production test coupon requirement) for below details--
 
Construction Code :  ASME SEC VIII DIV 1
 
Shell Material :   SA 387 GR 12 CL 2,  65 & 70 Thk.
 
MDMT :  0 Deg Celcius
 
Impact test is required as per  ASME SEC VIII DIV 1.
 
The Heat number for shell material for 3 vessels is not same.
 
 
3 vessels are required to be fabricated as per the above requirement for single  client. The vessels are going to to be erected at one location only. 
 
The thichkness of shell material for 1 vessel is 65 Thk and for other 2 vessels is 70 Thk. Diameter and Length of the vessel is different. Only MDMT and material is same.
 
Please inform me whether seprate  PTC( production test coupon)  is required for each  vessel  OR 1 PTC attached with longseam/Circ. Seam of only 1 vessel  will also represent other 2 vessels also.
 
Whether 2 PTC ( 1 for longseam &  1 for circumferential seam for 1 vessel)  is enough for all three vessels OR total of 6 PTC are required for 3 vessels.
 
Please give code reference.
 
Thanks in advance for your valuable suggestions.
 
Regards
 
Asad Azmi
 
 
 
 

Shadab Alam Ansari

unread,
Nov 27, 2010, 2:21:44 AM11/27/10
to material...@googlegroups.com

Dear Asad,

Please see the flow chart prepared by me according to ASME Sec-VIII Div. 1 for PTC.

Please correct me if anything is wrong.

 

Best regards,

 

Shadab Alam Ansari

Welding Engineer

 

cid:image001.gif@01CB80C0.5B165EE0

For Gulf Heavy Industries Co

One of  Al-Bassam Group of Companies

 

Cell Phone No: 00966502090165, Fax No:0096633410105
Telephone No: 0096633400098 (5 Lines) Ext: 232

Email: ans...@ghi.com.sa

Web: "www.ghi.com.sa"

 

Save paper, don't print any emails unnecessarily. Let's save environment for future generation....

--
To post to this group, send email to material...@googlegroups.com
To unsubscribe from this group, send email to materials-weld...@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

image001.png
image002.gif

r.kesav moorthi

unread,
Nov 27, 2010, 8:35:55 PM11/27/10
to material...@googlegroups.com
Dear,
you need all 6 PTC 's to qualify the production weld of LS & CS joints of vessels.

 
175, R.Kesavamoorthi,
Principal surveyor,
Quest (pvt.) Ltd.,
Ranipet.

yoga nandhan

unread,
Nov 28, 2010, 11:12:47 AM11/28/10
to material...@googlegroups.com
Dear Mr.Asad Azmi,

1. For each vessel, one test plate shall be made for each welding procedure used for joints of Categories A and B. ( If u use same process for A & B category, one PTC is sufficient).

2. If u consider the group of vessel, then the following have to be satisfied to avoid multiple PTC. (below is from UG-84(i)3(b))

For several vessels or parts of vessels, welded within any 3 month period at one location, the plate thickness of which does not vary by more than 1⁄4 in. (6 mm),or 25%, whichever is greater, and of the same specification and grade of material, a test plate shall be made for each 400 ft (120 m) of joints welded by the same procedure.
(if u go by this option, a seprate log to be maintained for day to day welding activities including each welder productivity, consumables consumption.)

3. The vessel impact test plate shall be from one of the heats of steel used for the vessel or group of vessels.

Regards
P.Yoganandhan



--
To post to this group, send email to material...@googlegroups.com
To unsubscribe from this group, send email to materials-weld...@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.



--
Regards
Yoganandhan.P

JASPAL SINGH

unread,
Nov 28, 2010, 11:22:18 PM11/28/10
to Materials & Welding
Dear Asad Azmi,

My Point wise Reply for your Query is as follows

- The Thickness of your vessels is within the requirements of
UG-84(6mm or 25% of the thickness)
- Practically I think the welding of these three vessels will not be
possible within three month span for all 'A' & 'B' Catagory Joints, if
your production schedule is possible you can go for lesser number of
PTC.
- Eraction at Single site has no advantage the fabrication should be
done at same location for three vessels.
- As the heat number is not same but material specification is same
you can choose the material from any one heat.
- The Seperate PTC requirement will not be due to Long(A) & Circ
Seam(B). The difference will be as per Position and Procedure.
- I assume you will use two procedure one of SMAW & other of SAW
welding.
Final Solution:
1. Select the material of PTC of 70mm thick from any heat, Weld the
same with SMAW in 3G Position it will cover all the positions ( i.e
Long & Circ Seams of Shell, Doller & Pettal Seam of Dish if any)( But
be careful due to high heat input Impact may fail)( Do the welding 3G
only if required otherwise weld in the required position). If the
welding completes within 3 month no need to weld other with manual
otherwise weld one more coupon to cover another three months.
2. Select the PTC of 70 mm thick and weld with SAW welding in the 1G
positon , this will cover for Long & Circ Seams. The same way if
welding required to be covered for next three month weld one more test
coupon.
3. So with Four test coupon you can comply the ASME Section VIII
requirements.
4. Please be care full if there is any Long & Circ Seams in the Nozzle
with different thickness and procedure is different you need to have
PTC for that also.

Hope the things will be clear to you.

Regards

Best Regards,

JASPAL SINGH CWI-AWS, CSWIP-3.1
Head Quality Assurance-ISGEC-PED, Yamunanagar, Haryana (India) PH:
+911732307251 ; Mob. +918930111441(CUG), +919996624244


On Nov 28, 6:35 am, "r.kesav moorthi" <k7moor...@yahoo.co.in> wrote:
> Dear,
> you need all 6 PTC 's to qualify the production weld of LS & CS joints of vessels.
>
>  
> 175, R.Kesavamoorthi,
> Principal surveyor,
> Quest (pvt.) Ltd.,
> Ranipet.
>
> From: asad azmi <azmiasada...@gmail.com>
> To: material...@googlegroups.com
> Cc:
> Sent: Friday, 26 November, 2010 4:30:01 PM
> Subject: [MW:8391] production test coupon requiorement as per ASME SEC VIII DIV 1
>
> Dear all,
>  
> Greetings.
>  
> Please inform me PTC(Production test coupon requirement) for below details--
>  
> Construction Code :  ASME SEC VIII DIV 1
>  
> Shell Material :   SA 387 GR 12 CL 2,  65 & 70 Thk.
>  
> MDMT :  0 Deg Celcius
>  
> Impact test is required as per  ASME SEC VIII DIV 1.
>  
> The Heat number for shell material for 3 vessels is not same.
>  
>  
> 3 vessels are required to be fabricated as per the above requirement for single  client. The vessels are going to to be erected at one location only. 
>  
> The thichkness of shell material for 1 vessel is 65 Thk and for other 2 vessels is 70 Thk. Diameter and Length of the vessel is different. Only MDMT and material is same.
>  
> Please inform me whether seprate  PTC( production test coupon)  is required for each  vessel  OR 1 PTC attached with longseam/Circ. Seam of only 1 vessel  will also represent other 2 vessels also.
>  
> Whether 2 PTC ( 1 for longseam &  1 for circumferential seam for 1 vessel)  is enough for all three vessels OR total of 6 PTC are required for 3 vessels.
>  
> Please give code reference.
>  
> Thanks in advance for your valuable suggestions.
>  
> Regards
>  
> Asad Azmi
>
> --
> To post to this group, send email to material...@googlegroups.com
> To unsubscribe from this group, send email to materials-weld...@googlegroups.com
> For more options, visit this group's bolg athttp://materials-welding.blogspot.com/

Dindo

unread,
Nov 29, 2010, 10:36:08 AM11/29/10
to material...@googlegroups.com
Hello Azmi
 
Long time no see.
 
If you can satisfy UG-84, it doesnt necessarily means that you need to complete everything within three months, you just need to start welding within the three months period. That's how we do it in Alberta, Canada anyway.
 
 
Regards
Ricardo
For more options, visit this group's bolg at http://materials-welding.blogspot.com/

PURUSHOTHAMAN N

unread,
Aug 16, 2013, 3:18:27 AM8/16/13
to material...@googlegroups.com
Dear all,

1. Flange Long. seam joint required PTC or not.
2. PTC required for category C & D joints.
please give a code reference for above two points.

Regards
Paul

CHINTUKUMAR GANDHI

unread,
Aug 16, 2013, 7:15:22 AM8/16/13
to material...@googlegroups.com
Dear all,

Please refer UG-84 (i) of ASME Sec. VIII-1 Ed. 2010, Add. 2011a.

Thanks & regards,

C. R. GANDHI


From: PURUSHOTHAMAN N <puru...@gmail.com>
To: material...@googlegroups.com
Sent: Friday, August 16, 2013 12:48 PM
Subject: [MW:18442] Re: production test coupon requiorement as per ASME SEC VIII DIV 1

--
To post to this group, send email to material...@googlegroups.com
To unsubscribe from this group, send email to materials-weld...@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/

 
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-weld...@googlegroups.com.
For more options, visit https://groups.google.com/groups/opt_out.


Reply all
Reply to author
Forward
0 new messages