This is required during scraping the pipeline by the inspection instrument scraper / Calliper Run.
Regards,
Sohaib
Dear all,
6mtr is the minimum length requirement for the pup piece,
But using 6 mtr pup piece in every 1 KM of pipe line is not a requirement (or mandatory), and any client will not recommend also ( As per my previous experience)
Request you verify / provide the spec of the client if available.
Thanks & Regards
Lakshman kumar.B |
Manager - QA/QC | LANCO INFRATECH LIMITED