Yes you are correct for the piping, but the subject discussion was for a pressure vessel designed as per ASME Sec VIII div1.
From: material...@googlegroups.com [mailto:material...@googlegroups.com] On Behalf Of Ranasaria Shivanand Rajendra
Sent: Thursday, September 13, 2007
4:58 PM
To: material...@googlegroups.com
Subject: [MW:225] RE: 224] RE:
213] RE: 206] PWHT for joint of two differentthk - 43 mm to 36mm
Hi Gents,
I feel the criteria mentioned in e-mail below, may not be true for Process Piping ( as per ASME B31.3).
As per ASME B31.3 Clause 331.1.3, PWHT is required for Thickness > 19 mm.
For connection of two pipes of different thickness, higher thickness of the two pipes should be considered for PWHT of the joint.
If anyone feels otherwise, please comment.
Also it may be noted that there are a little different criteria applicable for branch welds covered in clause 331.1.3a.
Regards,
Rana
Shivanand R Ranasaria
Contact +971 2 502 2058
From: material...@googlegroups.com [mailto:material...@googlegroups.com] On Behalf Of Bathula
Raghuram (Mumbai - PIPING)
Sent: Thursday, September 13, 2007
9:46 AM
To: material...@googlegroups.com
Subject: [MW:224] RE: 213] RE:
206] PWHT for joint of two different thk - 43 mm to 36mm
However I forgot to mention, Welds on Dished end (by seeing the dia it is not seamless) and attachment (nozzles), if any could require PWHT.
From: material...@googlegroups.com [mailto:material...@googlegroups.com] On Behalf Of Bathula
Raghuram (Mumbai - PIPING)
Sent: Monday, September 10, 2007
9:18 AM
To: material...@googlegroups.com
Subject: [MW:213] RE: 206] PWHT for
joint of two deifferent thk - 43 mm to 36mm
See UW-40(f) (5) (a)
When a welded joint connects parts of unequal thicknesses, the nominal thickness is the thinner of two adjacent butt-welded parts including head to shell connections.
Hence PWHT is not required required for this joint, but Preheat shall be maintained @ 95 deg.C.
Raghuram Bathula
From: material...@googlegroups.com [mailto:material...@googlegroups.com] On Behalf Of Agrawal Sunil (Mumbai -Stequ)
Sent: Saturday, September 08, 2007
12:39 PM
To: material...@googlegroups.com
Subject: [MW:206] PWHT for joint
of two deifferent thk - 43 mm to 36 mm
My equipment is having the following condition:
MOC: Carbon steel
Dished end: 4500 dia x 43 thk
Shell : 4500 dia x 36 thk
As per code, dished end is to be PWHT. Shell is exempted.
My query is whether PWHT is necessary for circumferential joint of dished end to shell (43 thk dished end welded to 36 thk shell)?
My understanding is at the joint itself, thickness is 36 mm which need not to be PWHT as per code, however, taper portion (HAZ) of dished end will be more than 38 thickness and hence may required PWHT.
Please guide me.
Best Regards,
Sunil Agrawal
EDTICB-Mumbai (STEQU)
Ph.: +91 22 6777
7237
Background:
We have a LTCS pipe upto 45 mm which are internally coated by FBE ( Tuboscope TK 236 ) and welded by special manufacturer’s techniques ie using Thru Kote Sleeves by Tuboscope, exact details of TK236 & Thru Kote Sleeves re attached.
These Sleeves make sure tht during welding, heat do not burn the internal FBE coating on pipe, it’s a proven technique in use by Maersk Qatar.
However As the pipes are above 19 mm , as per B31.3 we are supposed to have a PWHT.
When I wrote to Tuboscope regarding this issue there response was as below
“ The max. allowance temperature for TK-236 is 200°C. The same is for the Blue Mastic and max. 100°C for the NBR O-rings.
For the PWHT you need min. 250 - 300°C over a longer time so you will have the problem with the destruction of the coating.”
We have addressed this issue to Client, Client’s response is that Thickness upto 25.4 mm can be waived off, but for higher thickness, EPC contractor has to find a solution.
Question:
As PWHT is not feasible on internally FBE coated pipe, can Code help us to get a justifiable waiver with some improved welding procedure etc or by any other ways.
________________________________
It is better to go for an ROV for field joint coating, these were used in RPL Jamnagar way back in year 1997-98, i am sure there will much improvement in this field now
For the underground epoxy coated lines (Sea water intake), filed joint coating was done with the help of a robotic head ( i don't remeber the vendor who has done it might be from UK), even smaller dia like 4"-6" line filed welds were coated using this. The head has an inbulit multi purpose attachement ( at three different locations) which can do various operations simulatenously, blasting and cleaning the weld spatter/slag, paint application, and drying. these are monitored remotely thro optic fibre cables and LCD,s.
I am sure it should be availeble in Gulf too.
For PWHT probably the improved heating element like this will give you less damage to the coated area.
www.pih.co.uk/uploads/files/induction_heat.pdf
<http://www.pih.co.uk/uploads/files/induction_heat.pdf>
On Sep 15, 11:54 am, "Bathula Raghuram \(Mumbai - PIPING\)"
> winmail.dat
> 9KDownload
Be a better Heartthrob. Get better relationship answers from someone who knows.
Yahoo! Answers - Check it out.