Hydrotesting Pressure gauge calibration

533 views
Skip to first unread message

Praveen Kumar

unread,
Nov 25, 2010, 1:22:48 AM11/25/10
to material...@googlegroups.com

Dear All,

 

Can you pls Suggest as the Piping Hydrotesting Pressure gauge calibration period of time,

and also is there any code/stds governing for this.

 

 

 

Regards,

 

Praveen Kumar

Mechanical Engineer

 

Karthik

unread,
Nov 25, 2010, 2:13:24 AM11/25/10
to material...@googlegroups.com
Hi,
Pressure gauge calibration time shall be in every 6 months as per the normal practice and various project specifications.

Thanks & Regards,

(Karthik)

Karthikeyan.S
QA/QC Manager
Getabec Energy Co.,Ltd.
379,Moo6,Soi8,Nikhomphatana,
Rayong-21180,
Thailand.
Phone: 0066 38 897035-8 (Off)
Fax: 0066 38 897034
Hand Phone: 0066 892512282


--- On Thu, 11/25/10, Praveen Kumar <praveenk...@gmail.com> wrote:
--
To post to this group, send email to material...@googlegroups.com
To unsubscribe from this group, send email to materials-weld...@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

Muni Andy

unread,
Nov 25, 2010, 3:20:21 AM11/25/10
to material...@googlegroups.com
Dear Mr.Praveen,
As per Indian Standard IS 3624,It is to be calibarated once in 3 months.
You can refer the customer or relevant applicable spec.
C.Muniyandi
Surveyor

--

Sundaram Elumalai

unread,
Nov 25, 2010, 3:57:24 AM11/25/10
to material...@googlegroups.com

Some Client – ARAMCO requires every 30 days. Please check your client spec also.

 

With Kind regards,

S.Elumalai.


manoj vernekar

unread,
Nov 25, 2010, 4:21:48 AM11/25/10
to material...@googlegroups.com
Shell/PDo before every test,
 
End of the day client specification to be followed
 
manoj

Manoj.Vernekar

Richard Bonardo

unread,
Nov 25, 2010, 5:17:03 AM11/25/10
to material...@googlegroups.com
Dear Karthik :

I have a complicated situation with pressure gauge calibration period.

During calibration test, our gauge found to be showing wrong reading (below actual). And clients ask to re-test all spool pipe tested using the gauge.

My question, is that acceptable ? luckily there are only small number of spool to be re-tested, but I cant imagine if that happens to spools that already put in service.re

Just a share, but I appreciate any coments and advise.

Best Regards
Bonardo



From: Karthik <karth...@yahoo.com>
To: material...@googlegroups.com
Sent: Thu, 25 November, 2010 2:13:24 PM

Subject: Re: [MW:8373] Hydrotesting Pressure gauge calibration

muthu barathi

unread,
Nov 25, 2010, 5:49:38 AM11/25/10
to material...@googlegroups.com
Hi,

Ststutatory requirements depend upon mfrs. recommendation, clients requirement, or continuously used more than 4 times or while testing if there is any more difference than tolerance or calibrated test certificate reading or not working properly during test or any damage or more heat zone then you have to recalibrate and compare reading . if it goes beyond tolerance or acceptable limit of std engineering procedure simply throw it and replace with new calibrated by accredited body such as NABL approved labs.



On Thu, 25 Nov 2010 15:48:55 +0530 wrote

>Dear Karthik :

I have a complicated situation with pressure gauge calibration period.

During calibration test, our gauge found to be showing wrong reading (below actual). And clients ask to re-test all spool pipe tested using the gauge.

My question, is that acceptable ? luckily there are only small number of spool to be re-tested, but I cant imagine if that happens to spools that already put in service.re

Just a share, but I appreciate any coments and advise.

Best Regards
Bonardo


From: Karthik

To: material...@googlegroups.com
Sent: Thu, 25 November, 2010 2:13:24 PM
Subject: Re: [MW:8373] Hydrotesting Pressure gauge calibration

Hi,
Pressure gauge calibration time shall be in every 6 months as per the normal practice and various project specifications.

Thanks & Regards,

(Karthik)

Karthikeyan.S QA/QC Manager Getabec Energy Co.,Ltd. 379,Moo6,Soi8,Nikhomphatana, Rayong-21180, Thailand. Phone: 0066 38 897035-8 (Off) Fax: 0066 38 897034 Hand Phone: 0066
892512282

--- On Thu, 11/25/10, Praveen Kumar wrote:
Dear Sir,





Thanking You,

Honesty is the best Policy

With Warm Regards,

Muthu Barathi P
Mobile No:00962788269821 (Jordan)
00962775401951

Priya Deshmukh

unread,
Nov 26, 2010, 12:03:28 AM11/26/10
to material...@googlegroups.com
Dear Pravin,
 
I think pressure gauge calibration period depends upon the extent of use of the pressure gauge or the client specification. It needs to be stated in your quality control system.
 
But one think which is needed is pressure gauge verification or calibration after hydrotest to check whether there is any damaged that was caused to the gauge during hydrotest.
 
If it shows out of calibration. The test needs to be repeated again with proper pressure gauge.
 
Regards,
 
Priyanka Deshmukh.
Engineer QAC.

On Thu, Nov 25, 2010 at 11:52 AM, Praveen Kumar <praveenk...@gmail.com> wrote:
--
To post to this group, send email to material...@googlegroups.com
To unsubscribe from this group, send email to materials-weld...@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.



--
Priyanka Deshmukh,
Quality Control Engineer,
Transparent Energy Systems Pvt. Ltd.

sohale ikram

unread,
Nov 25, 2010, 4:39:10 AM11/25/10
to material...@googlegroups.com
Best practice is get to calibrated before every test but keeping in mind the commercial aspects a six month time period or client specs can be followed. it  also depends on how many times you are using the gauge in the stipulated time period.
 
Best regards
Sohale


From: Sundaram Elumalai <Elumalai...@starfab.com.sa>
To: material...@googlegroups.com
Sent: Thu, November 25, 2010 12:57:24 PM
Subject: RE: [MW:8375] Hydrotesting Pressure gauge calibration

Rajakrishnakanth, SA

unread,
Nov 25, 2010, 6:58:41 AM11/25/10
to material...@googlegroups.com
Hi Bonardo,
To avoid these type of situations,always connect two pressure gauges sothat
even one pressure gauge shows wrong reading,the other one will help.

Thanks & Regards
S.A.Rajakrishnakanth
Senior Manager Inspection
Jacobs Engineering India Pvt Ltd.,
Chennai
Land line : +91-44-42014380.
Mobile No : 09677166021

-----Original Message-----
From: material...@googlegroups.com on behalf of Richard Bonardo
Sent: Thu 11/25/2010 3:47 PM
To: material...@googlegroups.com

Best Regards
Bonardo


Thanks & Regards,


(Karthik)

NOTICE - This communication may contain confidential and privileged
information that is for the sole use of the intended recipient. Any viewing,
copying or distribution of, or reliance on this message by unintended
recipients is strictly prohibited. If you have received this message in
error, please notify us immediately by replying to the message and deleting
it from your computer.

winmail.dat

murugesan jeyaraman

unread,
Nov 25, 2010, 8:07:31 AM11/25/10
to material...@googlegroups.com
In general calibration every six months acceptable, or you can go for every  three months calibration. or else you can go according to client specs.
 
If your projects is such a multi million project,  and  you are having pipe spools in thousand or two thousand plus spools, and pre fabrication itself extends to long period such as one to two years. You can go for six months outside calibration, with internal calibration of every two weeks or one week, by buying a pressure applying gauge to your pressure gauges and can have internal calibration.
 
Thanlks
 
Murugesan

Karthik

unread,
Nov 25, 2010, 8:37:13 PM11/25/10
to material...@googlegroups.com
Hi,
This might happen sometimes even though within the calibration period due to sudden increase or decrease of pressure.You have to advice/ask your pressure test team/person to increase or decrease the pressure gradually as shown on your pressure test procedure and chart.Sudden increase or decrease shall effect the pressure gauge performance and result in wrong readings.
For your case,You have to retest all the spools where you have used that particular pressure gauge.



Thanks & Regards,

(Karthik)

Karthikeyan.S
QA/QC Manager
Getabec Energy Co.,Ltd.
379,Moo6,Soi8,Nikhomphatana,
Rayong-21180,
Thailand.
Phone: 0066 38 897035-8 (Off)
Fax: 0066 38 897034
Hand Phone: 0066 892512282


--- On Thu, 11/25/10, Richard Bonardo <bonar...@yahoo.com.au> wrote:

Arunachalam A

unread,
Nov 25, 2010, 11:58:16 PM11/25/10
to material...@googlegroups.com
Logically, if the test gauge shows a pressure reading below the actual test pressure during calibration, means during actual hydrotest, the spools are tested at a higher pressure than actual test pressure. 

So logically, no need to test the spools again.

arun
அருணாசலம்
கலைவாணி
சுதர்ஷனா
வருண்


Reply all
Reply to author
Forward
0 new messages