Post heating. Not required
Preheat maintenance, according to ASME IX, is not post heating
Preheat maintenance means that you do not cool down before perform PWHT
B31.1 requires preheat maintenance for Pno15E unless engineering provides differently
This message contains confidential information. To know more, please click on the following link: http://disclaimer.bureauveritas.com
Preheat maintenance is not "post heating".
This non essential variable applies only if PWHT shall follow
This variable (non essential) is not applicable to GTAW.
---