I have query on pressure vessels manufactured as per PED requirement.
 
To comply PED requirement is it mandetory to qualify welders & welding procedure under NOBO or RTPO? or They can review & approve welder qualfication & welding procedure qualified under any TPI?
 
 
Regards
Romio

Prakash Gotimukul

unread,
Jun 12, 2014, 8:27:49 AM6/12/14
to material...@googlegroups.com
They have to be qualified by NOBO which has under their scope Qualification of welders because not all NOBO have such qualifications.

Rgds
G.Prakash
Independent Consultant, ASME AIS


--
To post to this group, send email to material...@googlegroups.com
To unsubscribe from this group, send email to materials-weld...@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
 
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-weld...@googlegroups.com.
For more options, visit https://groups.google.com/d/optout.

Manivannan Hemu

unread,
Jun 14, 2014, 5:28:07 AM6/14/14
to material...@googlegroups.com
Hi,
qualification process to be done under NOBO or RTPO.
You can get clear understanding through the official guideline published in this regards by WPG of PED is given below: