Dear Experts
WPS for 6GR could be developed via 6GR coupon in accordance with AWS D1.1.
However, sample test or tubular mock-up test is required from time to time.
1st question
Are they mandatory for all 6GR qualification test?
2nd question
Can fabricator select test method, sample test or tubular mock-up ?
Your prompt advice would be highly appreciated.
--