Dear Sirs,
As per ASME B31.3 clause no.341.3.1(a) mentioned P Nos.3,4,5A,5B,5C AND 15 materials examination(RT/UT) shall be performed after completion of heat treatment. But no information for P1 material whether NDT performed before or after PWHT.
Please advise can we perform NDT(RT/UT) before PWHT activity for P1(NACE/H2 service) material or not.
Regards,
Ranajit Chatterjee
9995018265
--
To view this discussion visit https://groups.google.com/d/msgid/materials-welding/1497495186.2548454.1788859744262%40mail.yahoo.com.
--
To view this discussion visit https://groups.google.com/d/msgid/materials-welding/CAERJn6AENBHsSB5H8eW%3D9moPtzZwAS_v%2BT1VjnLDbf3BZ3Pa8Q%40mail.gmail.com.
To view this discussion visit https://groups.google.com/d/msgid/materials-welding/CAJzm4eODNKux-7abV1hCdipOzfV8_kPRDqh0Yj_ECfvmdHX5NA%40mail.gmail.com.
So, if it is an NACE/H₂S service line, the project specification may require a final NDE after PWHT, even though
B31.3 itself does not mandate it for P-No. 1.
Welding → RT/UT → PWHT → final RT/UT → hardness check, where hardness control is an important means of
controlling SSC susceptibility in carbon and LA steel weldments.
The first RT/UT is useful for finding weld defects. PWHT changes the weld metallurgy and residual stress condition.
Final RT/UT (for a sour-service line with mandatory PWHT) could be an additional project/engineering requirement.
Hence, you can decide based on your needs.
C. Sridhar.
-------------------------------------------------------------------------------------------------------------------------