Hi Sagar,
As per ASME31.3, you will find PWHT before RT, But suggestion is to you follow your Project Specification or other wise Construction Code of your project.
Same issue came in our project also.
Regards,
Ahmed
--
To post to this group, send email to materials-wel...@googlegroups.com
To unsubscribe from this group, send email to
materials-weld...@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and
meant for educational purposes only, Users must take their own decisions w.r.t.
applicable code/standard/contract documents.
Asper B31.3 2007 Edn...No need of PWHT upto 20 mm thickness.
On 11/15/10, ahmed <ah...@costaindas.ae> wrote:
> Hi Sagar,
>
>
>
> As per ASME31.3, you will find PWHT before RT, But suggestion is to you
> follow your Project Specification or other wise Construction Code of your
> project.
>
> Same issue came in our project also.
>
>
>
> Regards,
>
> Ahmed
>
>
>
> _____
>
> From: material...@googlegroups.com
> [mailto:material...@googlegroups.com] On Behalf Of Sagar QC
> Sent: Monday, November 15, 2010 10:21 AM
> To: material...@googlegroups.com
> Subject: [MW:8267] PWHT and RT
>
>
>
> Hi,
>
>
>
> I have a doubt regarding PWHT and RT. We are welding P1 Material Pipes which
> has thickness more than 19mm so we are performing PWHT for the same. But my
> question is regarding when to take RT? Can we accept the joints which is
> radiographed before PWHT and MPI after PWHT. Or will we have to perform the
> RT only after PWHT of the joints? Please advice me regarding this and
> provide the supporting clause.
>
>
>
> Thanks and Regards,
>
> Sagar.
>
> --
> To post to this group, send email to material...@googlegroups.com
> To unsubscribe from this group, send email to
> materials-weld...@googlegroups.com
> For more options, visit this group's bolg at
> http://materials-welding.blogspot.com/
> The views expressed/exchnaged in this group are members personel views and
> meant for educational purposes only, Users must take their own decisions
> w.r.t. applicable code/standard/contract documents.
>
> --
> To post to this group, send email to material...@googlegroups.com
--
To post to this group, send email to material...@googlegroups.com
To unsubscribe from this group, send email to materials-weld...@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
Thanking you,
Best regards,
Shadab
Hi, No.Welder need requalification for Overlay welding.welder shall be requalified for each 6 months of each welding process.If he has not do welding in 6 months on any qualified process his qualification will be discontinued on the particular process. Thanks & Regards, (Karthik) Karthikeyan.S QA/QC Manager Getabec Energy Co.,Ltd. 379,Moo6,Soi8,Nikhomphatana, Rayong-21180, Thailand. Phone: 0066 38 897035-8 (Off) Fax: 0066 38 897034 Hand Phone: 0066 892512282 --- On Mon, 11/15/10, Shadab Alam Ansari <ans...@ghi.com.sa> wrote: |
|
As per B31.3, it is not necessary to do the RT for P1 material after PWHT.
Regards,
|
--
To post to this group, send email to material...@googlegroups.com
To unsubscribe from this group, send email to materials-weld...@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
This case always depends on application.
The election between PWHT + NDT or NDT+PWHT+NDT is a decision to take according to the criticality of service, the specific experience of welding workshop, welders skill, time schedule, costs, etc.
About PWHT:
Considering the above reasons NDT is preferable after PWHT to make sure the weld quality.
NDT + PWHT + NDT:
"RT before PWHT" would be an optional additional examination. Some folks do this do make sure the joint will pass RT prior to doing the PWHT. In some cases, if "RT before PWHT " is a requirement, it may be included in purchase order/specification.
If you noticed repair after PWHT, then you need repair and re-PWHT required;to minimise/avoid this situation, preferable choice is NDT+PWHT+NDT. Repair work with re-PWHT may affect time schedule and cost impact also.
Customers always interested in NDT acceptance after PWHT.
PWHT + NDT:
However, have found that some contractors will tend to pay more attention to detail if they only shoot one RT after PWHT. Nobody wants to have to repair and perform a second PWHT.
--
To post to this group, send email to material...@googlegroups.com
To unsubscribe from this group, send email to materials-weld...@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
Thanks & Regards
S.A.Rajakrishnakanth
-----Original Message-----
From: material...@googlegroups.com on behalf of G Padmanabhan
Sent: Sat 11/20/2010 6:24 PM
To: material...@googlegroups.com
Subject: Re: [MW:8336] PWHT and RT
Dear Sagar,
As ASME/ANSI B31.3 2007 Edition,Thickness greater than 20mm only PWHT
required.NDT before or after PWHT depends upon your project specificaiton.
ASME B31.3 silent on ndt before or after pwht for P1 materials.
General good industrial practice is NDT after PWHT prefered.
On Mon, Nov 15, 2010 at 11:50 AM, Sagar QC <sagarqcw...@gmail.com>wrote:
> Hi,
>
> I have a doubt regarding PWHT and RT. We are welding P1 Material Pipes
> which has thickness more than 19mm so we are performing PWHT for the same.
> But my question is regarding when to take RT? Can we accept the joints
which
> is radiographed before PWHT and MPI after PWHT. Or will we have to perform
> the RT only after PWHT of the joints? Please advice me regarding this and
> provide the supporting clause.
>
> Thanks and Regards,
> Sagar.
>
> --
> To post to this group, send email to material...@googlegroups.com
> To unsubscribe from this group, send email to
>
materials-weld...@googlegroups.com<materials-welding%2Bunsubscrib
e...@googlegroups.com>
> For more options, visit this group's bolg at
> http://materials-welding.blogspot.com/
> The views expressed/exchnaged in this group are members personel views and
> meant for educational purposes only, Users must take their own decisions
> w.r.t. applicable code/standard/contract documents.
>
--
With Warm regards,
G.Padmanabhan
+96895685853
--
To post to this group, send email to material...@googlegroups.com
To unsubscribe from this group, send email to
materials-weld...@googlegroups.com
For more options, visit this group's bolg at
http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and
meant for educational purposes only, Users must take their own decisions
w.r.t. applicable code/standard/contract documents.
NOTICE - This communication may contain confidential and privileged information that is for the sole use of the intended recipient. Any viewing, copying or distribution of, or reliance on this message by unintended recipients is strictly prohibited. If you have received this message in error, please notify us immediately by replying to the message and deleting it from your computer.
Hi Mr.Sagar
For asking support clause, please refer below:
Based on below as per B31.3, P1 material not required NDE after completion of Heat treatment and this point not mentioned in code legibly; but mentioned in interpretation 19-15 (refer attachment)
a) (a) Refer Para 341.3.1(a)
“For P-Nos. 3, 4, and 5 materials, examination shall be performed after completion of any heat treatment”
b) (b) Refer Note (11) in “NOTES FOR APPENDIX A TABLES “
“For use under this Code, radiography shall be performed after heat treatment”
This note(11) pointing P3, P4, P5A, P5B, P9A & P9B materials only as per table A-1.
c) (c) Refer B31.3 interpretation 19-15, Question(2) (refer attachment)
“P1 or P2 materials not required NDE after final Heat treatment”
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-weld...@googlegroups.com.
To post to this group, send email to material...@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/8511fb39-08df-4240-b373-399fd200da40%40googlegroups.com.
For more options, visit https://groups.google.com/d/optout.
--